Summer IT Project Update
Tech Talk
September 11, 2007
Wireless Networking
Wireless network access available
campus-wide
Over 220 access points
Work still underway in Fine Arts Center,
Allen Center, Sparks Center, Center Hall,
small houses, some outdoor spaces
Improved guest access and high-security
options will be available later this fall
Usage stats: week | month
Computer Lab Upgrades
New computers installed in Library
computer lab, Baxter 214
New high-speed printers installed in
Library computer lab, Library reference
area, and both Armory labs
Academic Projects
Physics mobile computer lab (15
Macbook laptops) replaced
Installed Stata (statistical software
package) in computer labs
LabView for Physics
Present Indiana summer projects
Creating group work area on 1st floor of
Lilly Library (in progress)
Classroom Upgrades
New projectors installed in 16 classrooms
New computers installed in 18 classrooms
Supercarts installed in 33 classrooms
(work ongoing)
New projection systems in Detchon 220,
Library 3rd floor seminar room (coming
soon)
Summer Tech School
21 classes offered
Approximately 150 attendees
72 people completed online evaluation
form
95.8% rated workshop “excellent” or
“good”
90.1% would definitely recommend the
workshop to another person
Media Center
Created dual-boot iMac Lab
Apple TV, with instructional videos
Editing stations have Apple monitors,
providing better color-matching
Implemented new student worker
training program
Enhanced podcasts coming soon to
podcasts page
Online Services
New home page (debuts later today)
Fraternity web pages
Real-time online honor roll
Video virtual tour (coming soon)
Sports site enhancements | livestats
Networking Projects
Network upgrades for College Hall, Delta
Tau Delta
Traffic shaping methodology changed
Upgrading Blackboard server hardware (in
progress)
Beginning process to connect Wabash to iLight state-wide network
Phone system upgraded – new features
available this fall
Tape backup system
Installation in progress
Two LTO-3 Ultrium 960 drives
48 media slots
800GB storage capacity per tape
38.4TB total storage capacity
Maximum transfer rate 1.1TB/hour
Storage Area Network
Installation in progress
Provides 12 terabytes of
data storage
Allows for server
virtualization, which reduces
hardware costs and
improves redundancy
Data snapshots reduce
backup and recovery time
Administrative Computing
Upgrade to Colleague R18
Migrated to Datatel’s New User Interface
Licensed Activities and Events module
for advancement office
Computer Installations
235 new computers installed
New web-based installation schedule
process
Off-lease laptop computers sold through
lottery system (300 entries for 65
computers)
To reduce equipment costs, most
monitors were retained
Equipment Disposal
Recycled 22,525 pounds
of broken and obsolete
equipment with
Recycle Force (Indy)
Planning community
recycle day this fall
Windows Vista/Office 2007 Support
Vista and Office 2007 supported for
student use
Campus computers will be upgraded in
summer 2008
Vista remote access instructions will be
posted to web site soon
See knowledge base for information on
reading Office 2007 files in Office 2003
Miscellaneous
Added 12 Canon G7 digital cameras to
checkout pool
Added 2 Canon ZR850 digital video
cameras to checkout pool
Migrated to new version of Exact Target
(bulk email program)
Implementing web-based printing
solution that will allow printing to campus
printers without special computer setup