ANNEXURE 7 PROJECT SPECIFIC ENVIRONMENT

advertisement
ANNEXURE 7
PROJECT SPECIFIC ENVIRONMENT MANAGEMENT PLAN
PROJECT SPECIFIC EMP DURING CONSTRUCTION PHASE
During construction phase following precautions will be taken to prevent the possible hazards
and nuisance to the surrounding locality.
AIR ENVIRONMENT:
• We have used two nos. of tanker water for dust suppression on plot during excavation
period.
• There was provision for washing of wheels of truck and vehicles to dislodge the adhered
mud prior to exit the site.
• Easy traffic movement will be maintained by deploying adequate security personnel. Entry
and exit of heavy vehicles as well as neighbouring traffic will be monitored by security
personnel
• Vehicles with proper PUC certificate will be allowed to enter the site
• Strictly ‘No Horne Policy’ will be followed in and around the site. No loading or unloading
activity will be carried out at the night time.
• High Speed diesel will be used.
• All the trucks will be covered with tarpaulin to avoid dust pollution
WATER ENVIRONMENT:
• 10 nos. of mobile toilets will be provided for the labours on site.
• No discharge of construction wastes to ground water bodies had been allowed during
construction
NOISE ENVIRONMENT:
• The work timing will be strictly adhered. No construction activity will be allowed after
10.00 pm and before 6.00 am.
• DG sets with acoustic enclosure and adequate stack height will be provided.
• Electrically operated construction equipment’s will be used to reduce the noise pollution.
• Strictly “No Horne Policy” will be followed in and around the site. No loading or unloading
activity will be carried out at the night time

200 nos. of Ear plugs will be made available to Workers
SOIL/LAND ENVIRONMENT:
• Top soil will be stockpiled temporarily for replacement whenever required.
• Disposal of the construction way debris: Construction debris, Waste concrete and broken
bricks will be utilized in low-land levelling, secondary concrete, below roads. Some quantity
of Excavated soil will be used for backfilling and remaining will be disposed on our other plot
situated at Anshul ELA Gat no. 50/1, near toll plaza, Moshi, Pune.
• Restrictions will be put on burning of solid waste on site.
• Green belt will be developed around the periphery of the plot to minimize the impact of
construction activity
HEALTH & SAFETY:
• Safety barricades and signage will be placed at strategic location.
• Proper fencing will be put in place as a safety precaution and barrier.
• PPE will be provided for all the labors and asked to follow the safety policy strictly.
• First-aid and health check-up facility will be provided to the labors.
• Awareness programs will be conducted regarding personnel safety, occupational safety,
health, hygiene, environmental resource conservation, etc.
PROJECT SPECIFIC EMP DURING OPERATION PHASE
MANAGEMENT OF AIR ENVIRONMENT:
• 1No. 250 kVA and 1No. 380 kVA. D.G. Sets will be installed with acoustic measures as per
CPCB norms and Generator exhaust will be taken implemented to mitigate impacts from
fugitive emissions.
MANAGEMENT OF WATER ENVIRONMENT:
• Adoption of dual plumbing system
• Water reuse and recycle practices will be adopted (48 % recycling will be achieved)
• Treated Sewage will be used for landscaping & flushing
• Effective rain water harvesting system will be implemented
• Proper storm water drainage network will be provided within project site
MANAGEMENT OF NOISE ENVIRONMENT:
• Periodic maintenance of machinery and vehicles should be undertaken to reduce the noise
impact
• The sources of intermittent noise generating equipment (pumps for lift or water pumping, DG
sets etc) will be provided with appropriate acoustic barriers so that the noise level within 100
m of these facilities when in operation will be less than 70 dBA
• Implementation of landscaping (194 nos of trees), horticulture etc., are expected to reduce
noise impacts within the project premises.
MANAGEMENT OF LAND/ SOIL ENVIRONMENT:
There will not be any impact on the land environment during operation phase.
Solid waste will be generated during operation phase. This solid waste collected in room after
segregated and composted in Composting machine. Non-biodegradable waste handed Over to
PCMC.
MANAGEMENT OF TRAFFIC:
• There will be enough space for movements of vehicles and parking, thus the traffic
management on the project site will be easily and smoothly monitored without any hindrance
to the regular flow of traffic on the main road
• Six gates, for entry and exit, will be provided.
• Flow of traffic is eased out by providing adequate entries and exits from basement and surface
parking areas
• Entry and exit managed by security personnel who will also regulate traffic
ENVIRONMENTAL MANAGEMENT PLAN BUDGETARY ALLOCATION
EMP DURING CONSTRUCTION PHASE
Sr. No.
1.
2.
3.
4.
5.
6.
Parameter
Personnel Protective Equipment (Qty.)
Site Sanitation Facility
Drinking water facility, water sprinkling
Solid waste management
Safety railing, platform, ladder, hoist, cranes etc.
House keeping
Total Cost/ year
(Rs. Lakhs)
5.00
5.00
10.00
12.00
10.00
2.00
7.
8.
Health Check
Environmental Monitoring
Total Cost
5.00
10.00
59.00
EMP during Operation Phase
Sr. No.
EMP Measures
1.
Sewage Treatment Plant
Capital Cost
(Rs. Lakhs)
134.50
2.
Rain Water Harvesting
12.63
0.63
3.
Solid Waste Management
32.25
11.61
4.
Gardening & Landscaping
51.00
7.00
5.
Electrical Measures
281.95
6.58
6
Environment Monitoring
17.5
2.00
529.83
58.38
Total
O & M Cost/Year
(Rs. Lakhs)
30.56
ENVIRONMENT MONITORING PLAN
DURING CONSTRUCTION PHASE
Sr.
No.
Item
1.
Ambient Air
Quality
2.
3.
Parameters
Frequency
Location
PM10, PM2.5, SO2, NOx
Quarterly
At major construction
area. ( total 4
locations)
Noise Level
Equivalent noise
Level dB(A)
Monthly
At major construction
area.
Water
Analysis
Physical, chemical and
Bacteriological
parameters
Quarterly
Tankers
Frequency
Location
Quarterly
Total 4 locations
around periphery of
the site.
DURING OPERATION PHASE
Sr.
No.
Item
Parameters
1.
Ambient Air
Quality
PM10, PM2.5, SO2,
NOx
2.
Noise Level
Equivalent noise
level
Quarterly
Near DG sets, Near
STP, Near parking
area, Near Gate
3.
Exhaust from
DG Set
SO2, NOx , SPM
Quarterly
Stack of DG sets.
4.
Water
Analysis
Physical, chemical and
Bacteriological
parameters
Weekly
during rainy
season and
quarterly
during dry
season
Domestic water tank
5.
Wastewater
Analysis
pH, BOD, COD, TSS,
TDS, O & G
Fortnightly
STP