02200 - nycsca

advertisement
12/05/14
DESIGN No. _____
1
2
SECTION 02200
EARTHWORK
PART 1 - GENERAL
1.01 DESCRIPTION OF WORK
A.
17
20
4
3
23
Excavate for new construction, fill and backfill as
required, prepare subgrades and place aggregate bases
for slabs, walks, and pavements. Protect all adjoining
properties
and
existing
structures
from
damage.
Perform Work in conjunction with Section 02100 and
other related Sections.
B.
Implement the erosion and sediment control plan for use
during construction activities such as excavation,
grading, backfilling, etc. and modify as needed
dependent on actual activities. The plan, prepared
primarily for combating erosion and sedimentation
caused by rainfall and surface run-off, shall include
control measures commonly used for compliance with the
requirements set by the New York State Department of
Environmental Conservation (DEC) for a basic Storm
Water Pollution Prevention Plan (SWPPP).
Incorporate
into the plan the erosion control measures indicated to
be performed on the Contract Documents.
C.
Execution
of
this
Work
will
contaminated
soil or debris.
conjunction with Section 02081.
encounter
Perform
asbestos
work in
23 1.02 RELATED SECTIONS
21
A.
Building Demolition....................Section 02060
B.
Asbestos Abatement.....................Section 02081
C.
Site Preparation.......................Section 02100
D.
Foundation and Other Change
Adjustments....... ....................Section 02250
E.
Pile Foundations.......................Section 02360
F.
Landscaping............................Section 02900
1.03 SUSTAINABILITY REQUIREMENTS
A.
NYCSCA
The Contractor shall implement practices and procedures
to meet the Project’s sustainable requirements. The
Contractor shall ensure that the requirements related
to these goals, as defined in Specification Section
S01352, Sustainability Requirements, and as specified
in this Section, are implemented to the fullest
extent.
Substitutions or other changes to the work
EARTHWORK 02200 - 1
12/05/14
DESIGN No. _____
shall not be proposed by the Contractor or their subcontractors if such changes compromise the stated
Sustainable Design Performance Criteria.
B.
Sustainability requirements included in the Section are
as follows:
1.
Sediment and erosion control plan and narrative.
2.
Documentation
measures.
3.
Documentation of Recycled concrete aggregates.
4.
Documentation of Regional materials.
of
sediment
and
erosion
control
1.04 REFERENCES
References and industry standards listed in this Section are
applicable to the Work. Unless more restrictive criteria or
differing
requirements
are
explicitly
stated
in
the
Specifications,
or
mandated
by
governing
codes
or
regulations,
the
recommendations,
suggestions,
and
requirements described in the referenced standards shall be
deemed mandatory and applicable to the Work.
A.
American Society of Testing
standards, latest editions.
and
Materials
(ASTM)
D422 Standard Test Methods for Particle-Size Analysis
of Soils.
D1556 Standard Test Method for Density of Soil in Place
by the Sand-Cone Method.
D1557 Standard
Test
Method
for
Moisture-Density
Relations of Soils and Soil-Aggregate Mixtures
Using 10-lb (4.54-kg) Rammer and 18-in. (457mm)
Drop.
D2167 Standard Test Method for Density and Unit Weight
of Soil In-Place by the Rubber Balloon Method.
D2922 Standard Test Methods for
Soil-Aggregate
in
Place
(Shallow Depth).
B.
Density of Soil and
by
Nuclear
Methods
New York State Department of Environmental Conservation
STARS Memo #1 Petroleum-Contaminated
Soil
Guidance
Policy entire part except Sections III and IV), last
revised August 1992
CP-51: Soil Cleanup Guidance Policy, Issued 10/21/2010
(effective 12/3/2010
NYCSCA
EARTHWORK 02200 - 2
12/05/14
DESIGN No. _____
DER-10 Technical Guidance for Site Investigation and
Remediation, Issued 5/3/2010 (effective 6/18/2010)
C.
New York Code of Rules and Regulations (NYCRR):
6 NYCRR Part 360, Solid Waste Management Facilities
6 NYCRR Part 364, Waste Transporter Permits
6 NYCRR Part 370, Hazardous Waste Management System –
General
6 NYCRR Part 371,
Hazardous Wastes
Identification
and
Listing
of
6 NYCRR Part 372, Hazardous Waste Manifest System and
Related Standards for Generators, Transporters and
Facilities
6 NYCRR Part 373, Hazardous Waste Management Facilities
6 NYCRR Part 375, Environmental Remediation Programs
D.
United States Department of Transportation (USDOT):
49 CFR 172, Subpart C - Shipping Papers
49 CFR 172, Subpart D – Marking
49 CFR 172, Subpart E - Labeling
49 CFR 172, Subpart F - Placarding
49 CFR 172, Subpart G - Emergency Response Information
49 CFR 173,
Packagings
General
Requirements
for
Shipments
and
49 CFR 177, Carriage by Public Highway
E.
United States Environmental Protection Agency (USEPA):
40 CFR Part 261,
Hazardous Waste
Identification
and
Listing
of
40 CFR Part 262, Standards Applicable to Generators of
Hazardous Waste
40 CFR Part 263, Standards Applicable to Transporters
of Hazardous Waste
40 CFR Part 264 , Standards for Owners and Operators of
Hazardous
Waste
Treatment,
Storage,
and
Disposal
Facilities
NYCSCA
EARTHWORK 02200 - 3
12/05/14
DESIGN No. _____
40 CFR Part 265,
Interim Status Standards for Owners
and Operators of Hazardous Waste Treatment, Storage,
and Disposal Facilities
F.
United States Department of Labor (USDOL), Occupational
Safety and Health Administration (OSHA):
29 CFR 1910, Occupational Safety and Health Standards
28
G.
All
Applicable
New
York
City
Department
of
Environmental Protection (NYCDEP) Rules and Regulations
H.
All
applicable
New
York
City
Department
of
Transportation (NYCDOT),
Department of Sanitation
(NYCDOS), Department of Buildings (NYCDOB), and Transit
Authority (NYCTA) Rules and Regulations
1.05 DEFINITIONS
A.
Excavation
Excavation is considered unclassified and consists of
removal of material encountered to contract level,
stockpiling, testing, loading, handling, transporting
and subsequent legal disposal of such.
B.
Improvements
Man-produced items such as concrete, brick, asphalt,
piping, etc. Those items not naturally occurring.
C.
Non-Hazardous Excavated Material
Material that may include or contain mixtures of the
following: soil (including, but not limited to, natural
undisturbed material), debris, concrete and concrete
products (including steel or fiberglass reinforcing
rods that are embedded in the concrete), asphalt
pavement, brick, glass, rock, municipal solid waste,
refuse, and incidental ash.
This material includes
material defined in Title 6 New York Code of Rules and
Regulations 360-7.1(b)(1)(i) and will exceed 6 NYCRR
375-6 Unrestricted Use and Restricted Use Soil Cleanup
Objectives and NYSDEC CP-51: Soil Cleanup Guidance
Supplemental Soil Cleanup Objectives.
19
All material excavated from the site is assumed to meet
the definition of non-hazardous excavated material.
D.
Petroleum-Contaminated Material
Material (soil, concrete, sediment, UST contents, fill,
debris, etc.) that meets the NYSDEC STARS Memo #1
definition of petroleum-contaminated material from
known source areas.
Petroleum-contaminated material
shall be evidenced by the following observations and be
NYCSCA
EARTHWORK 02200 - 4
12/05/14
DESIGN No. _____
from a known source area:
producing higher than
background responses on a portable vapor meter such as
a photo ionization detector or flame ionization
detector, petroleum-like odor, visual impacts (e.g.,
staining or discoloration), proximity to known releases
from existing or historic petroleum storage tanks or
systems, and exceed the soil cleanup levels for
gasoline and/or fuel oil contaminated soil provided in
the
NYSDEC
CP-51: Soil Cleanup Guidance.
The
determination as to whether the excavated material is
petroleum-contaminated or is non-petroleum contaminated
material will be made by analytical testing of
representative material samples. All sampling shall be
performed under the supervision of the Authority’s IEH
Division or its representative. The Contractor shall
provide the Authority’s IEH Division with qualitative
and quantitative information, and the IEH Division
shall make the final determination as to whether or not
the
material
is
petroleum-contaminated
and
the
appropriate disposal.
E.
Hazardous Waste
Material
meeting
the
definition
of
a
Resource
Conservation and Recovery Act hazardous waste as
defined in 40 CFR Part 261, New York State ECL Section
27-09 or 6 NYCRR Part 371.
F.
Environmentally Clean Fill and Backfill
1.
26
NYCSCA
For fill and backfill proposed for use as cover
material (landscaped areas of the site within 2
vertical
feet
of
the
final
surface
grade
elevation), environmentally clean fill is defined
as soil that has been tested utilizing methods
which yield laboratory reporting limits that are
below the regulatory comparison criteria and found
to contain:
a.
No detectable concentrations
organic compounds;
of
volatile
b.
No other organic compounds or inorganic
analytes at concentrations above 6 NYCRR
375-6
Unrestricted
Use
Soil
Cleanup
Objectives; and
c.
No other organic compounds or inorganic
analytes at concentrations above the lower of
the NYSDEC CP-51: Soil Cleanup Guidance
Residential Use, Protection of Ecological
Resources, and Protection of Groundwater
Supplemental Soil Cleanup Objectives.
d.
For sites with no ecological resources (as
described
in
CP-51,
Section
V.C.)
the
EARTHWORK 02200 - 5
12/05/14
DESIGN No. _____
Supplemental Soil Cleanup Objectives for
Ecological Resources shall not apply.
The
determination regarding whether ecological
resources are present shall be made by the
IEH Division of the Authority.
2.
For fill and backfill proposed for use below cover
material (as defined in the previous paragraph)
and underneath areas with no potential for public
contact
(e.g.,
floor
slabs
and
pavement),
environmentally clean fill is defined as soil that
has been tested utilizing methods which yield
laboratory reporting limits that are below the
regulatory
comparison
criteria
and found to
contain:
a.
No detectable concentrations
organic compounds;
of
volatile
b.
No other organic compounds or inorganic
analytes at concentrations above the lower of
DER-10
Technical
Guidance
for
Site
Investigation and Remediation, Appendix 5,
“Allowable Constituent Levels for Imported
Fill or Soil” Restricted Residential Use and
Ecological Resources Soil Cleanup Objectives;
and
c.
No other organic compounds or inorganic
analytes at concentrations above the lower of
the NYSDEC CP-51: Soil Cleanup Guidance
Residential Use, Protection of Ecological
Resources, and Protection of Groundwater
Supplemental Soil Cleanup Objectives.
d.
For sites with no ecological resources (as
described in CP-51, Section V.C.) the Soil
Cleanup Objectives for Ecological Resources
shall not apply. The determination regarding
whether ecological resources are present
shall be made by the IEH Division of the
Authority.
1.06 SUBMITTALS
10
14
A.
NYCSCA
Product Data
1.
Provide
manufacturer's
information
on
the
compaction equipment to be used on each type of
material for review.
2.
Filter fabric for silt fence
EARTHWORK 02200 - 6
12/05/14
B.
Shop Drawings
1.
Submit shop drawings and associated calculations
for sheeting, shoring, bracing and underpinning.
Shop drawings and calculations shall be signed and
sealed by a New York State licensed professional
engineer.
2.
Submit engineer’s report on dewatering scheme
along with associated drawings and calculations.
3.
Erosion and Sediment Control Plan along with a
written narrative.
Incorporate into the drawings
and narrative erosion control measures indicated
to be performed on the Contract Documents.
4.
Silt Fence
27
5.
A Community Air Monitoring Plan in accordance with
the requirements of paragraph 3.02H.
C.
22
Samples
D.
Quality Control Submittals
20
14
DESIGN No. _____
Provide a 15 pound bag of each material used for
imported fill, backfill, aggregate base, gas permeable
aggregate, crushed stone, broken stone ballast to the
Authority's testing laboratory.
1.
Design Data
Provide the following information:
22
2.
31
NYCSCA
a.
Gradation analysis for fill materials.
b.
Gradation analysis for aggregate bases.
c.
Gradation analysis for crushed stone.
d.
Gradation analysis for broken stone ballast.
e.
Material composition
concrete material.
analysis
f.
Gradation
aggregate.
for
analysis
gas
of
recycled
permeable
Existing Conditions Survey
Submit existing conditions survey and monitoring
plan consisting of various data described in
Article 3.02 of this Section.
Monitoring Plan
shall be prepared in accordance with Section
BC 3309.16
of
the
2014
NYC
Building
Code.
EARTHWORK 02200 - 7
12/05/14
DESIGN No. _____
Monitoring Plan for underpinning work shall
prepared in accordance with Section BC 1814.3.
3.
4.
be
Certificates
a.
Provide certificate guaranteeing fill and
backfill
material
used
for
construction
conforms to the samples supplied and the
requirements of this section.
b.
Provide certificate guaranteeing aggregate
materials used for construction conforms to
the gradation supplied and the requirements
of this section.
c.
Provide facility permits, material acceptance
requirements,
and
waste
analytical
requirements
for
each
proposed
off-site
disposal
facility
that
conform
to
the
requirements of this section.
d.
Provide a certification, along with the
testing
results
indicated
below
under
“Testing”, to the IEH Division for review and
approval from each proposed borrow area
stating that the imported fill and aggregate
are environmentally clean and each meet the
requirements
of
this
section
of
the
specifications
and
the
test
data
is
representative of the source.
The letter
shall also provide for each borrow area site:
street address; section, block and lot
numbers; and, a description of the current
and former uses of each borrow area site.
e.
Provide a certification at the time of
delivery of each load of environmentally
clean fill that the load was shipped to the
site directly from the Authority approved
source of environmentally clean fill.
This
certification shall show the name and address
of the source of each load, the license plate
number of the vehicle transporting the load,
and the time of departure of the load from
the source.
Contractor Qualifications
Provide proof of Contractor and Professional
Engineer qualifications specified under “Quality
Assurance”.
5.
Testing
a.
NYCSCA
Provide analytical testing of:
EARTHWORK 02200 - 8
12/05/14
DESIGN No. _____
26
b.
NYCSCA
1)
Existing material to
satisfy
requirements
facilities.
be removed to
of
disposal
2)
Borrow
(imported
fill)
material
to
verify it is environmentally clean fill
for use as cover material and for use
below cover material or underneath areas
with no potential for public contact.
Samples
shall
be
collected
at
a
frequency of no less than one sample per
500 cubic yards and shall be analyzed
for the full list of 6 NYCRR Part 375
and
NYSDEC
CP-51
Supplemental
Soil
Cleanup
Objectives
Parameters
(as
defined
above)
using
acceptable
laboratory reporting limits (below the
regulatory
comparison
criteria)
to
demonstrate that the soil complies with
the requirements for environmentally
clean fill.
3)
Existing material to be reused on-site
to verify that the material meets the
definition of environmentally clean fill
for use as cover material and for use
below cover material or underneath areas
with no potential for public contact.
Samples
shall
be
collected
at
a
frequency of no less than one sample per
500 cubic yards and shall be analyzed
for 6 NYCRR Part 375 and NYSDEC CP-51
Supplemental Soil Cleanup Objectives
Parameters (as defined above) using
acceptable laboratory reporting limits
(below
the
regulatory
comparison
criteria) to demonstrate that the soil
complies
with
the
requirements
for
environmentally clean fill.
Analytical testing shall be performed by a
New
York
State
Department
of
Health
Environmental
Laboratory
Approval
Program
(ELAP) certified laboratory engaged by the
Contractor.
Laboratory reporting limits
shall be acceptable to the Authority (i.e.,
below the regulatory comparison criteria).
Utilize “Template 1A or “Template 1B” as
directed by the Authority’s IEH Division
provided at the end of this section.
The
Contractor shall strictly adhere to the
format and content guidance of the IEH
Division template tables.
EARTHWORK 02200 - 9
12/05/14
DESIGN No. _____
6.
Documentation of Proper Disposal
Documentation acceptable to the Authority that
material removed from the site for disposal has
been disposed of at a facility approved by the
Authority.
E.
Excavated Material Disposal Plan
Excavated Material Disposal Plan prepared in accordance
with Article “Disposal of Excavated Material” of this
Section and good engineering practices.
Utilize
“Template 2” provided at the end of this section.
21
F.
Sustainability Submittals
1.
Sediment and erosion control plan and written
narrative, as provided in paragraph B.3 above.
2.
Documentation of implementation
sedimentation control measures:
3.
erosion
and
a.
Digital dated photos showing control measures
at each location on the plan.
b.
Inspection
logs
by
the
Contractor’s
Superintendent of the measures throughout the
project
and
descriptions
of
corrective
action.
Submit Contractor’s Sustainable Materials Form
with complete information on recycled content for
materials provided under the work of this section
in accordance with Section S01352, Sustainability
Requirements.
Include
cost
of materials and
percentage, by weight, of materials that have
post-consumer or pre-consumer recycled content.
a.
Recycled concrete aggregate
4.
Submit
documentation
of
recycled
consisting
of
product
data,
mix
information, or manufacturer’s statement:
5.
Submit Contractor’s Sustainable Materials Form
with complete information on regional content for
the following item provided under the work of this
section
in
accordance
with
Section
S01352,
Sustainability Requirements. Include cost of all
materials and distance in miles to point of
materials extraction and manufacture.
a.
6.
NYCSCA
of
content
design
Fill and backfill materials
Submit
documentation
of
regional
materials,
product data or material suppliers’ statement.
EARTHWORK 02200 - 10
12/05/14
DESIGN No. _____
1.07 QUALITY ASSURANCE
A.
Qualifications
1.
Company specializing in performing the Work of
this Section shall have a minimum of 3 years
experience and shall have worked on 3 projects of
similar size.
2.
Preparation of details of sheeting, shoring,
bracing and underpinning as well as monitoring
plans shall be under the direct supervision of and
bear the seal of a Licensed Professional Engineer
of the State of New York experienced in the design
of such work, who shall also be responsible for
filing
such
documents
and
the
construction
supervision of such.
31
B.
C.
Regulatory Requirements
1.
Work of this Section shall conform to all
requirements of the NYC Building Code and all
applicable regulations and guidelines of all
governmental
authorities
having
jurisdiction,
including, but not limited to, safety, health, and
anti-pollution regulations.
Where more stringent
requirements than those contained in the Building
Code or other applicable regulations are given in
this Section, the requirements of this Section
shall govern.
2.
Work outside the street line shall conform to the
requirements of the governmental authorities or
utilities having jurisdiction (i.e. DOT, DEP,
etc.).
Where more stringent requirements than
those provided by the applicable governmental
authority
are
given
in
this
Section,
the
requirements of this Section shall govern.
3.
Conform to the requirements of "Safety and Health
Standards, Subpart P - Excavations, Trenching and
Shoring" - OSHA.
4.
All fill and backfill must be environmental clean
materials
Regulatory Requirements
1.08 DELIVERY, STORAGE, AND HANDLING
A.
NYCSCA
Imported fill and aggregate materials to be used for
project are to be stockpiled separately at the
producer's
facility
and
shall
be
accessible
to
EARTHWORK 02200 - 11
12/05/14
DESIGN No. _____
inspection
Authority.
and
quality
control
(QC)
testing
by
the
B.
Stockpile material brought to the site prior to placing
in order to allow for testing by the Authority’s
testing laboratory.
Stockpile material in such a
manner as to prevent erosion and dust.
Provide silt
curbs if necessary.
C.
Testing
and
certification
of
all
environmentally clean fill and aggregate
responsibilities of the Contractor.
imported
are the
1.09 PROJECT/SITE CONDITIONS
A.
Existing Conditions
1.
NYCSCA
Site Information
a.
Obtain all Building Department data available
on the lot and those adjacent lots affected
or
being
affected
by
the
project
construction.
b.
The
Authority
makes
no
predictions
or
representations regarding the character or
extent of soil, rock, or other subsurface
conditions to be encountered during the work.
The Contractor shall make its own deductions
of the subsurface conditions that may affect
the methods or cost of construction of the
work hereunder, and agrees that it will make
no claims for damages or compensations,
except as are provided under the agreement
should the Contractor find conditions during
the progress of the work substantially
different
from
those
indicated
on
the
geotechnical
borings
provided
with
the
documents.
Additional borings and other
exploratory operations may be performed by
the Contractor, at the Contractor’s option
and following the Authority’s approval.
No
change in the Contract Sum will be authorized
for such additional exploration undertaken by
the Contractor.
c.
The subsurface information (borings or other
subsurface explorations) contained in the
Contract Documents were obtained primarily
for use in preparing the foundation design
and is included in the Contract Documents for
the convenience of the Contractor.
d.
Soil and/or groundwater data given on borings
or other subsurface explorations supplied by
EARTHWORK 02200 - 12
12/05/14
DESIGN No. _____
the Authority are not intended as warranties
of accuracy or continuity between soil
stratum.
Contractor
is
responsible
for
interpretations
or
conclusions
drawn
therefrom.
Additionally,
depth
to
water
measurements in environmental investigation
reports shall not be relied upon for bidding
purposes.
2.
Existing Utilities
a.
B.
Locate existing underground utilities:
1)
Provide adequate means of support and
protection
for
utilities
to
remain
during Work.
2)
Demolish
and
remove
underground
utilities designated to be removed.
Coordinate with utility companies for
shut-off services if lines are active.
b.
Consult immediately with the utility owner
for
directions
should
uncharted
or
incorrectly charted piping or other utilities
be encountered during excavation. Cooperate
with the utility owner, the Department of
Education, and owners of lots serviced by the
utilities
in
keeping
their
respective
services and facilities in operation. Repair
damaged utilities to the satisfaction of the
Utility Owner.
c.
Do not interrupt existing utilities serving
facilities
occupied
and
used
by
the
Department of Education or others during
occupied hours, except when permitted in
writing by the Department of Education and
the affected lot owners, and only after
acceptable temporary utility service has been
provided.
Do not proceed with interruption
of services without providing a minimum of 48
hours notice to the affected parties and
receiving their written approval.
d.
Coordinate
all
Work
Divisions 15 and 16.
with
the
Work
of
Coordination
Examine drawings to determine sequence of operations,
and relation to work of other trades.
Start of work
will signify acceptance of field conditions and will
acknowledge coordination with other trades.
NYCSCA
EARTHWORK 02200 - 13
12/05/14
C.
DESIGN No. _____
Foundations and Other Changes
The Authority reserves the right to change the design
of the foundation due to unforeseen soil conditions.
If the foundation design is so changed, the contract
price will be adjusted as set forth in Section 02250,
"Foundation and Other Change Adjustments".
1.10 SEQUENCING AND SCHEDULING
A.
Perform work in such a manner to ensure a minimum
interference with roads, walks, adjacent properties,
and facilities to remain open.
Do not close or
obstruct these items without obtaining permits from the
agencies having jurisdiction or the permission of the
adjacent owners.
B.
There shall be no petroleum-contaminated material
and/or
hazardous
waste
excavation
and
handling
activities performed when the existing building is in
use by the Department of Education or others during
occupied hours, except when permitted in writing by the
Authority.
PART 2 - PRODUCTS
14
22
2.01 MATERIALS
A.
26
B.
Restricted Excavated Material
Remove all debris not explicitly designated to be
salvaged (to remain) from improvements and soil
excavated during construction from premises and legally
dispose of away from premises as part of the base bid.
Any environmentally clean fill (as defined in paragraph
1.05F and tested to meet such requirement) meeting the
gradation requirements of Paragraph B below may be
reused on the site pending credit to the Authority.
Fill and Backfill
Only
environmentally
clean
fill
(as
defined
in
paragraph 1.05F) shall be used as fill and backfill.
All fill and backfill shall be material classified as
controlled fill by the New York City Building Code.
Composition shall consist of a mixture of angular sands
and gravels.
Flat structured material such as mica
(the main component of “mole” rock) falling into the
acceptable gradation or other material affecting the
permeability and structural characteristics of the sand
material shall be no more than .4% of the total
material. Material shall not contain salts or foreign
materials of any kind and the material shall show a
percentage of wear by the Los Angeles wear test (ASTM
C131) of not more than 35%. These fill materials shall
NYCSCA
EARTHWORK 02200 - 14
12/05/14
DESIGN No. _____
contain no particles exceeding 3" in the largest
dimension. No more than 30% of the material by weight
shall be retained on a 3/4” sieve.
No more than 10%
shall pass the No. 200 sieve by weight. The Contractor
shall provide the Authority with laboratory data on
material proposed for use as fill/backfill.
Samples
shall be collected from imported material and material
proposed for reuse on-site.
The Contractor shall
collect and analyze one representative sample of each
material for every 500 cubic yards of imported
fill/backfill brought to the site or material proposed
for reuse on-site for the complete list of 6 NYCRR Part
375
and
NYSDEC
CP-51
Supplemental
Soil
Cleanup
Objectives Parameters as defined in paragraph 1.05F.
C.
Aggregate Base
1.
Aggregate base course under pavements, driveways,
and slabs shall be composed of crushed ledge rock
(blue stone), roughly cubical or pyramidal in
shape,
and
sand
meeting
the
gradation
and
soundness requirements of New York State DOT, Item
3.04.02, Type 2.
Material shall be uniform in
quality and free of wood, loam, clay, dirt, roots,
bark, and any other extraneous material. Material
shall not contain salts or foreign materials of
any kind.
The aggregate shall be produced from
material showing a percentage of wear by the Los
Angeles wear test (ASTM C131) of not more than
35%.
2.
Stone shall have the following gradation:
25
Sieve
2"
1/4”
No. 40
No. 200
D.
NYCSCA
100
25-60
5-40
0-10
Crushed Stone
1.
25
Percent Passing by Weight
Crushed stone, to be used under interior slabs on
grade and backfill at narrow excavations, shall be
composed of crushed ledge rock (blue stone),
roughly cubical or pyramidal in shape, with a
gradation conforming to ASTM C33 No. 57 stone.
Material shall be uniform in quality and free of
wood, loam, clay, dirt, roots, bark, and any other
extraneous material.
Material shall not contain
salts or foreign materials of any kind.
The
aggregate shall be produced from material showing
a percentage of wear by the Los Angeles wear test
(ASTM C131) of not more than 35%.
EARTHWORK 02200 - 15
12/05/14
DESIGN No. _____
2.
Stone shall have the following gradation:
Sieve
Percent Passing by Weight
11/2"
1"
1/2"
No. 4
No. 8
E.
22
Gas Permeable Aggregate
1.
Gas Permeable Aggregate, to be used under building
floor slabs and as shown on the Drawings shall be
composed of gravel, crushed gravel, and crushed
stone, roughly cubical or pyramidal in shape. Gas
permeable aggregate shall be uniform in quality
and free of wood, loam, clay, mica, dirt, roots,
bark, and any other extraneous material.
Gas
permeable aggregate shall not contain salts or
foreign materials of any kind. Material selected
for use as gas permeable aggregate shall be
composed of particles which will not be reduced in
size due to forces exerted on the material during
placement and construction as by the Los Angeles
wear test (ASTM C131).
2.
Gas Permeable Aggregate shall be Tilcon “Straight
3/4-inch Stone”, New York Sand & Stone “School
Construction Authority Gas Permeable Aggregate”,
110 Sand “3/4-inch gravel”, or Authority-approved
equal
meeting
the
following
gradation
requirements:
Sieve Size
1”
3/4"
1/2”
7
F.
Percent Passing by Weight
95-100
30-60
0-5
Broken Stone Ballast
1.
NYCSCA
100
95-100
25-60
0-15
0-5
Broken stone ballast, to be used to stabilize poor
soils, shall be composed of crushed ledge rock
(blue stone), roughly cubical or pyramidal in
shape, with a gradation conforming to ASTM C33 No.
3 stone. Material shall be uniform in quality and
free of wood, loam, clay, dirt, roots, bark, and
any other extraneous material. Material shall not
contain salts or foreign materials of any kind.
The aggregate shall be produced from material
showing a percentage of wear by the Los Angeles
wear test (ASTM C131) of not more than 35%.
EARTHWORK 02200 - 16
12/05/14
DESIGN No. _____
2.
Stone shall have the following gradation:
Sieve Size
Percent Passing by Weight
21/2"
2"
11/2"
1"
1/2”
G.
Recycled Concrete Aggregate
1.
As an option, recycled concrete aggregate may be
used instead of ledge rock for aggregate base,
crushed stone, and broken stone ballast (meeting
the indicated gradations for each), depending on
the soundness of aggregates, which are at the
Engineer of Record's option. The material must be
clean, with no deleterious material visible (wood,
brick, metal, or other friable material) and meet
the following criteria:
a.
Material shall consist of at least 99% by
weight of Portland cement concrete or ledge
rock.
b.
Material making up the remaining 1% shall be
as follows:
c.
H.
1)
Wood - 0.1% maximum
2)
Brick, mica schist, metal, or other
friable stone material - 0.4% maximum
3)
Asphaltic Concrete - 1% maximum
Material shall be environmentally clean (as
defined in Paragraph 1.05F.
Silt Fence
1.
Filter Cloth:
a.
Harris Silt Fence
b.
Stabilinka T140N
2.
Woven Wire Fence: Minimum 15 gauge, maximum 6”
mesh spacing
3.
Fence Posts:
a.
NYCSCA
100
90-100
35-70
0-15
0-5
Steel either
Hardwood
“T“
or
“U”
type
or
2”X4”
EARTHWORK 02200 - 17
12/05/14
DESIGN No. _____
2.02 EQUIPMENT
A.
Provide proper compaction equipment to properly compact
subgrade, fill and backfill, gas permeable aggregate,
aggregate base, crushed stone and broken stone base.
Subgrade compaction requirements are indicated in those
sections.
Employ a Licensed Professional Engineer to
determine soil type and which equipment will give the
proper compaction.
2.03 SOURCE QUALITY CONTROL
A.
Tests
The Authority's Testing Laboratory
following laboratory tests:
B.
will
perform
the
1.
Sieve Analysis: Performed in accordance with ASTM
D422 on submitted fill samples to verify material
meets
gradation
requirements.
In addition,
recycled concrete aggregate will be examined for
materials conformance.
2.
Moisture Density Curve: Optimum moisture content
obtained from submitted fill samples, tested in
accordance with ASTM D1557.
Inspection
1.
2.
Testing Laboratory
a.
The Authority will engage an approved Testing
Laboratory or Special Inspection Agency to
perform laboratory tests and field compaction
testing on the fill/backfill materials and
subgrade.
b.
The Laboratory will be responsible to and
under the supervision of a Special Inspector.
Special Inspection
The Authority will assign, under the requirements
as defined in Chapter 1 Title 28 of the NYC
Administrative Code and Section BC 1704.7 of the
2014 NYC Building Code, a Special Inspector to
supervise the testing of the controlled filling
operations and approval of the subgrade bearing
capacity,
as
well
as
and
inspection
of
underpinning
and
shoring
operations
as
per
Sections BC 1704.20.3 and BC 1704.20.2.
NYCSCA
EARTHWORK 02200 - 18
12/05/14
DESIGN No. _____
3.
Contractor’s Responsibility
Inspections
and
testing
performed
by
the
Authority’s
agent(s)
shall
not
relieve
the
Contractor of responsibility for performing all
other testing and inspection specified herein or
otherwise necessary to meet the quality control
and
quality
assurance
requirements
of
this
Section.
PART 3 - EXECUTION
3.01 EXAMINATION
A.
Verification of Conditions
Verify existing site conditions match those of the
survey or pre-bid inspections. Notify the Authority in
writing
prior
to
commencement
of
Work
of
any
discrepancies.
B.
Preparation
1.
Before starting any excavation work for new
construction, ascertain the exact locations of all
existing underground drain lines, piping, and
conduits. Consult with the Mechanical Trades.
2.
At location where any of the above services
interfere with the excavation work, notify the
Authority and the Mechanical Trade under whose
jurisdiction such work falls before continuing
with any more excavation.
3.02 PREPARATION AND PROTECTION
A.
Condition Survey
1.
General: The Contractor shall perform a condition
survey of the adjoining properties and existing
school building (if applicable) prior to beginning
excavation.
2.
Photographs:
Take photographs of the building
walls of the adjoining properties and existing
school (if applicable) so that the surfaces may be
examined during construction and compared with the
pre-work condition. If any cracks or other stress
signs are exhibited by the buildings, halt
operations
until
corrective
action has been
provided and is acceptable to the Authority.
3.
Monitoring
a.
NYCSCA
Retain
survey
a Licensed
of existing
Surveyor to provide a
conditions of adjoining
EARTHWORK 02200 - 19
12/05/14
DESIGN No. _____
properties
and
existing
school
(if
applicable).
Engage a Licensed Professional
Engineer to develop a monitoring plan, which
is to be implemented by the Contractor, as
required
by
Sections
BC
3309.6
and
BC 3309.4.4.
Monitoring Plan shall be in
accordance
with
Section
BC 3309.16.
Monitoring Plan for underpinning operations
shall
be
in
accordance
with
Section
BC 1814.3.
31
30
NYCSCA
b.
Survey adjacent structures and improvements,
establishing exact elevations at fixed points
to act as benchmarks.
c.
Clearly
identify
benchmarks
and
record
existing elevations. Locate datum level used
to
establish
benchmark
elevations
sufficiently distant so as not to be affected
by
movement
resulting
from
excavation
operations.
d.
All work shall be laid out giving all points,
lines, and levels from established points on
the Drawings.
Elevations shall be verified
from existing benchmarks by the Surveyor.
e.
During
excavation,
resurvey
benchmarks
weekly, employing a Licensed Land Surveyor or
Licensed Professional Engineer.
Maintain
accurate log of surveyed elevations for
comparison with original elevations.
f.
Provide accelerometers on adjacent structures
prior
to
commencing
work.
Monitor
accelerometers
regularly.
During
installation of sheet or soldier piles,
monitor accelerometers continuously.
g.
Should
benchmark
readings
indicate
displacement
or
accelerometers
exceed
normally acceptable limits for particle
velocity (depending on condition of adjacent
structure and if the building is considered a
historic structure by the city or state),
halt operations until corrective action has
been provided and is acceptable to the
Authority.
EARTHWORK 02200 - 20
12/05/14
B.
DESIGN No. _____
Shoring, Sheeting, Bracing, and Underpinning
1.
29
NYCSCA
General
a.
Inspect site, examine existing conditions and
make all necessary preparations for the safe
and proper sequence of work.
b.
Properly guard and protect excavations so as
to prevent them from becoming dangerous to
person or property.
c.
Properly slope sides of excavation or provide
shoring, sheeting and bracing to prevent
caving, erosion, or gullying of sides of
excavations.
The sides of all excavations
that are 5 feet or greater in depth measured
from adjacent ground surface to the deepest
point, shall be protected to prevent the
sides
from
caving
in.
Alternatively,
excavation sides may be sloped not steeper
than 45 degrees.
d.
Brace, shore, and protect existing structures
when excavations are made adjacent to the
existing structures or within a distance that
they will be affected by the excavation.
Underpin adjacent structures when excavations
are carried to a depth that will require it
by the NYC Building Code or when indicated on
Drawings.
e.
Maintain sides and slope of excavation in
safe condition until backfilling or other
work is complete.
Maintain shoring and
bracing in place till completion of work.
Ensure that after all rainstorms all sides or
slopes of excavations are inspected as per
BC 3304.5.1 and safe conditions restored.
f.
Provide
materials
serviceable order.
g.
All shoring, bracing, sheet piling, etc. is
to be removed upon completion of the work
where they are installed, including any
portion thereof, outside of street and lot
lines.
Within the lot, remove all wood and
cut steel elements at a minimum to 4 feet
below grade.
Where they interfere with new
work and utilities, remove elements in their
entirety.
for
work
in
good
EARTHWORK 02200 - 21
12/05/14
DESIGN No. _____
2.
Inspection and Code Requirements
a.
Sheet piling, sheeting, shoring, bracing, and
underpinning for protection of excavations
and protection of adjacent structures and the
public
is
the
responsibility
of
the
Contractor
and
shall
comply
with
the
requirements of Section BC 3309, Protection
of Adjoining Property.
b.
The most stringent requirements of the
Building
Code,
Contract
Drawings,
Specifications, or any authorities having
jurisdiction shall govern this Work.
c.
Coordinate Work of this Section with Work of
all other Divisions so as to properly, and
completely, install all Work as drawn or
specified.
d.
The Contractor shall engage the services of a
third party Registered Professional Engineer
(not a direct employee) to prepare details of
underpinning, cofferdams, caissons, bracing,
sheeting, sheet piling, shoring, party wall
stabilization, and other construction as well
as
preparation
of
the
monitoring
plan
required for protection of excavations and
support of adjacent properties or buildings
as per Sections BC 1704.20.7, BC 3309.6 and
BC 3309.4.4.
These
drawings
shall
be
submitted to the Engineer of Record for
general review, which does not relieve the
Contractor's Engineer of responsibility for
the adequacy of the design.
e.
The Contractor's Engineer shall file Form
PW-1 with the Building Department, thereby
becoming the Engineer of Record for such
protection work and is responsible for
stability of all slopes and bracing and
underpinning and for preparation of all
design and shop drawings and their approval
by the Building Department.
The SCA will
engage a Special Inspection Agency to perform
the Special Inspections described in Sections
BC 1704.20.2, BC 1704.20.3, and BC 3304.4.1.
f.
As per Section BC 3304.3.1, no earthwork
within the property line shall commence
unless Contractor or permit holder notifies
the Department of Building via phone or
electronically within 24 to 48 hours prior to
the commencement of such work. Refer to the
Building Code for exceptions. The Contractor
31
NYCSCA
EARTHWORK 02200 - 22
12/05/14
DESIGN No. _____
shall preserve and protect from damage any
adjoining structures.
g.
When an excavation to a depth of 5 to 10 feet
is to be made within 10 feet of an adjacent
building or over 10 feet anywhere on the
site, the Contractor shall provide written
notice to the owner of the adjacent building
not less than 10 days prior to the starting
of excavation as per Section BC 3304.3.2.
The written notice shall describe the work,
timeframe
and
schedule
and
contact
information of the contractor and of the
department. No excavation shall commence
until the Contractor has documented the
existing conditions of all adjacent buildings
in a pre-construction survey.
24
h.
As per Section BC 3304.3.3, obtain approval
and permit from the NYC Department of
Environmental
Protection
prior
to
commencement of any drilling or excavation
activity greater than 100 feet (including
pile drilling) falling within 500 feet
horizontal distance from the centerline of a
water tunnel.
Provide notification to the
agency prior to commencement of actual
activities.
24
i.
As per Section BC 3304.3.4, obtain approval
and permit from the NYS Department of
Environmental
Conservation
prior
to
commencement of any drilling or excavation
activity greater than 500 feet.
Provide
notification to such the agency prior to
commencement of actual activities.
j.
As per Section BC 3304.3.5, obtain approval
and permit from the NYC Transit Authority,
Metropolitan Transit Authority, or the Port
Authority of New York and New Jersey prior to
commencement
of
any
excavation
activity
within 200 feet from any subway or tunnel
structure.
Provide notification to such
agencies prior to commencement of actual
activities.
24
C.
Water Control - Dewatering
1.
NYCSCA
Provide for the pumping and removal of all water
that is encountered on the Site at any location,
at any and all times, during the course of
construction
of
the
project
and
until
the
acceptance of the building. Prevent surface water
and subsurface or groundwater from flowing into
EARTHWORK 02200 - 23
12/05/14
DESIGN No. _____
excavations and from flooding the project site and
surrounding area in order to keep the site and
foundation subgrades dry.
16
NYCSCA
2.
No additional payment shall be made to the
Contractor for pumping and removal of water
required for installation of Work at the Contract
level.
This pumping and removal applies to all
water from any source whatsoever, and includes
subsurface or ground water, seepage, leakage,
drainage, trapped water, rain or snow, overflows,
etc., except for unforeseen water main breaks not
caused by the Contractor’s operations.
3.
Furnish
and
operate
all
pumping
equipment
necessary to protect against damage to all
structural installations subjected to hydrostatic
pressure. Consult geotechnical borings for water
levels. The groundwater table shall be assumed to
be at least 3 feet higher than the highest level
indicated on the borings as ground water levels
will fluctuate.
4.
Do not use sump pumps furnished under Division 15
for dewatering purposes.
5.
During excavation for and placing of pile caps,
footings, slabs, etc., the Contractor, at own
expense, shall maintain ground water to a depth
below the bottoms of the caps, footings, slabs,
etc. that will prevent softening of foundation
bottoms,
undercutting
of
footings, and soil
changes detrimental to stability of subgrades and
foundations.
6.
Provide and maintain pumps, well points, sumps,
suction and discharge lines, and other dewatering
system components necessary to convey water away
from the excavations, including all surface water.
Continue ground water dewatering until the caps,
footings, etc. are backfilled and till the
discontinuation of pumping will not endanger any
construction as determined by the Authority. The
structure shall be of adequate dead weight to
counterbalance the uplift force of the water
before discontinuation of dewatering.
Obtain
written
approval
from
the
Authority
before
subjecting the structure to hydrostatic pressure.
Such approval shall not relieve the Contractor of
responsibility for providing and maintaining the
structural integrity of the structure. Remove all
water from the building area.
7.
Engage a Professional Engineer licensed in the
state of New York knowledgeable in dewatering
systems to design the dewatering system.
The
EARTHWORK 02200 - 24
12/05/14
DESIGN No. _____
Engineer shall submit an Engineer's report to the
Authority for record keeping.
Include draw-down
curves and other such information.
Dewatering
operation shall be performed with supervisory
personnel who have had at least five years
experience in dewatering work. Maintain adequate
supervision and control to ensure that stability
of excavated and constructed slopes and trenches
are not adversely affected by water; erosion is
controlled; flooding of excavations or trenches,
or damage to structures does not occur.
NYCSCA
8.
Install and operate dewatering system or systems
in such a manner as to avoid the movement of fines
or loss of ground from below the bearing levels
and so as not to influence the stability of
surrounding areas.
Whatever method employed by
the Contractor shall include the facilities needed
to eliminate loss of ground.
9.
The Contractor shall utilize methods that minimize
drawdown and pumping rates, and comply with
dewatering permit.
10.
The Contractor shall be responsible for all
remedial action due to problems arising from
improper/illegal dewatering. The Contractor shall
obtain all permits from governing regulatory
agencies, including but not limited to New York
City Department of Environmental Protection (DEP)
and New York State Department of Environmental
Conservation (DEC), for dewatering and the offsite disposal of water.
11.
Dispose of water from site in such manner as will
not cause injury to the public health, nor to
public or private property, nor to the work
completed or in progress, nor to the surface of
the streets, nor cause any interference with the
use of the same by the public. Contaminated water
generated from dewatering activities shall not be
disposed
of
on
site.
At
a
minimum,
a
fractionation
tank,
oil/water
separator,
and
granular activated carbon adsorption system shall
be provided for treatment of contaminated water.
Prevent silting of storm sewers by using settling
tanks or other devices approved by the DEP. Clean
sewer lines that are to be used for disposal of
water
and
waste
during
construction.
The
Contractor
is
responsible
for obtaining all
necessary
permits
for
disposal
of
liquids
generated during dewatering operations and for the
pretreatment of all liquids as required for
disposal in accordance with all applicable rules
and regulations.
EARTHWORK 02200 - 25
12/05/14
D.
E.
DESIGN No. _____
12.
Place all dewatering and discharge pipes and hoses
that cross-traveled roadways in such a manner so
as to eliminate any disruption of traffic flow.
If so ordered by the Authority, place the pipe and
hoses in shallow trenches that shall then be
plated over.
Firmly secure all plates so as to
eliminate any possible shift or movement.
13.
Dewatering by means of well points or deep wells
will not be allowed in the Boroughs of Brooklyn or
Queens where the rate of pumping exceeds 45
gallons per minute unless the appropriate permit
has been secured from the New York State
Department of Environmental Conservation.
This
shall be done by the Contractor at own expense.
Frost Protection
1.
Furnish all facilities and materials needed to
prevent the earth and/or rock at bottom of
excavation from becoming frozen or unsuitable to
receive the footings and/or pile caps.
2.
Do not carry excavation to Contract levels during
freezing
weather
without
providing
complete
protection against freezing of the subgrade as
hereinafter
specified.
Provide
complete
protection against freezing if freezing weather
sets in after completion of the excavation to
Contract levels.
This protection shall include
adequate heating facilities and coverage of the
area to maintain temperatures above freezing until
footings and/or pile caps have been concreted and
backfilled.
Where backfilling results in less
than four feet of cover for the bottom of the
footing and/or pile cap, protect subgrade against
freezing.
3.
When excavations for footings, piers or pile caps
have been brought to the bottom elevations
indicated on the Drawings and the bottoms of these
excavations become frozen or otherwise unsuitable
in the opinion of the Special Inspector because of
inadequate protection by the Contractor, these
excavations shall be carried to lower depths
sufficient
to
provide
stable
bearings
as
determined by the Special Inspector and subject to
approval by the Engineer of Record and without
additional cost to the Authority.
Use of Explosives
The use of explosives shall be in strict conformance
with regulations governing such use by New York City
Department of Buildings and other authorities having
NYCSCA
EARTHWORK 02200 - 26
12/05/14
DESIGN No. _____
jurisdiction,
including
the
New
York
City
Fire
Department as per Section BC 3304.3.6. Explosives may
not be used without the written approval of the
Authority.
20
F.
Erosion & Sediment Control
Provide temporary erosion and sedimentation control
measures to prevent soil erosion and discharge of soilbearing water runoff or airborne dust to adjacent
properties
and
walkways.
The
Contractor
shall
formulate and carry out the Steps identified in a
balanced erosion and sedimentation control plan when
performing any land disturbance. Measures employed for
limiting soil erosion and off-site pollution caused by
sedimentation shall include, but not be limited to,
vegetative cover and/or sediment control devices.
1.
NYCSCA
Vegetative Control Measure:
Vegetation over an
area
slated
for
undergoing
excavation,
backfilling, or trenching is the best means for
containing soil loss. Seeds or mulch shall be
spread over a disturbed area that will remain open
for a long period before the next construction
activity begins.
Criteria for selecting seed
types for permanent vegetation shall be based upon
plant
adaptability
to
ground
conditions,
maintenance requirements or lack thereof.
a.
Quick
stabilization
of
sloped
and/or
disturbed ground shall be performed to ensure
the establishment of planted seeds.
Grading
and stabilization over a large construction
site shall not be delayed, pending the
completion of all activities for the project.
If necessary, soil stabilization or grading
efforts shall be phased according to a
phasing plan.
b.
Existing trees, shrubs, and other ground
cover is a buffer to soil erosion and they
shall be protected. During construction, the
Contractor shall exercise great care to
preclude damages to existing vegetation that
might be caused by construction equipment.
Construct barriers made of wood or steel to
surround trees and other vegetation.
c.
Workers at the construction site shall be
cognizant of the erosion and sediment plan
and shall be involved in guarding against
damages to vegetated areas caused by humans.
Use tape, signs and other methods listed in
the New York Guidelines for Urban Erosion and
Sediment Control to highlight seeded areas.
EARTHWORK 02200 - 27
12/05/14
DESIGN No. _____
2.
Sediment Control Devices
Displaced soil particles produced by rainfall or
surface run-off can have a harmful effect on the
environment and create clogging problems in the
drainage system. If vegetative cover is not
appropriate, a structural sediment control device
shall be employed to guard off against damages
caused by sedimentation.
Commonly used sediment control devices that are
also acceptable under the New York Guidelines for
Urban Erosion and Sediment Control include:
a.
Stabilized Construction Entrance
At
entrances
and
exit
points
to
the
construction site, provide a stabilized pad
of aggregates for capturing mud or sediment
that may be transported by vehicular traffic.
Use 2” stone or reclaimed concrete equivalent
that is well compacted over the sub-grade to
maintain the dimensions (width, length and
depth) of the site entrances and exits. Build
stabilized construction entrances having at a
minimum, 12” thick stone or layered recycled
concrete material with 12” depth. Replace
aggregates on an as-needed basis after
rainfall events.
b.
Silt Fence
Perimeter of disturbed area shall be fencedoff using a geotextile fabric (filter cloth)
similar to Harris Silt Fence to minimize
runoff velocity and limit damages caused by
carried over sediment. Construction of silt
fence
shall
conform
to
the
following
recommendations from the U.S Department of
Agriculture:
NYCSCA
1)
Woven wire fence (14½-gauge and max. 6”
mesh spacing) shall be fastened securely
to supporting posts using wire ties or
staples. Posts shall be 36” long and
driven into the ground at least 18”.
2)
Sedimentation filtering fabric similar to
Harris Silt Fence (geotextile material)
or an approved equal shall be fastened
securely to woven wire fence with ties
spaced every 24” at top and mid section.
EARTHWORK 02200 - 28
12/05/14
DESIGN No. _____
3)
c.
When two (2) sections of the filtering
fabric adjoin each other, they shall be
overlapped by 6” and folded.
Storm Drain Inlet Protection
Keep silting of underground storm drainage
piping from occurring and contain off-site
pollution caused by sediment laden run-off
using a permeable barrier around drain
inlets. Typical drain inlets protection to be
utilized include: (1) stone & block drop
inlet protection and (2) fabric drop inlet
protection
1)
Stone & Block Drop Inlet Protection
Build barrier made of blocks and stones
that reach at least one (1) foot high in
front of the storm drain inlet. The
block protection shall be constructed in
a manner that allows water to drain
through a few block openings. Use clean
stone or gravel 1/2" to 3/4" in diameter
placed 2” below the top of the block on
a 2:1 slope or flatter as recommended by
the U.S Department of Agriculture.
2)
Fabric Drop Inlet Protection
Another means for preventing clogging of
the drainage system caused by deposited
sediment is to build a protective
barrier made of filter fabric. Top of
the barrier shall be so arranged as to
enable overflow to drain into the
drainage structure. Supporting stakes
for the filtering fabric are necessary;
they shall measure 3 feet long and
surround the drainage structure in all
sides. Stakes materials shall be 2” x 4”
wood
or
equivalent
metal.
Burlap
material may be used temporarily as a
filtering fabric.
NYCSCA
3.
Inspect,
repair,
and
maintain
erosion
and
sedimentation control measures during construction
until permanent vegetation has been established.
4.
Remove erosion and sedimentation controls and
restore and stabilize areas disturbed during
removal.
5.
Document measures by digital photographs and logs
of inspections.
EARTHWORK 02200 - 29
12/05/14
G.
27
H.
NYCSCA
DESIGN No. _____
Workability of Excavation Subgrade
1.
Take all steps necessary to prepare or improve
existing conditions for proposed foundation work,
including
general
excavation
throughout
the
project site.
2.
Properly grade site and perform operations to
avoid disturbing the existing subgrade and any
intermediate subgrade.
3.
If subgrade conditions are disturbed that prevent
earthwork
operations
or
safe
operation
of
foundation installation equipment, the Contractor
shall take steps to improve subgrade conditions at
own expense. Many types of soils are sensitive to
disturbances
such
at
water
saturation
or
construction traffic and become unworkable.
Community Air Monitoring Program (CAMP) shall be in
effect during excavation work.
1.
Comply with the requirements of the following:
New York State Department of Health (NYSDOH)
Generic CAMP, Appendix 1A of NYSDEC DER-10.
2.
The Contractor shall prepare and submit to the
Authority
a
Community
Air
Monitoring
Plan.
Approval of the CAMP shall be required prior to
mobilizing to the site.
3.
Odor or dust complaints from any owner of an
adjacent or nearby property shall be managed by
the Contractor in a manner equivalent to an
exceedance of an action level in the CAMP.
4.
Ambient air monitoring shall be conducted upwind
and downwind of the excavation area at the
property perimeters for fugitive dust emissions
and organic vapors during periods of excavation,
placement of excavated materials in storage piles,
and loading of transporting vehicles. If readings
above established threshold levels are detected,
the Contractor shall institute measures to control
dust and/or organic vapors at no additional cost
to the Authority. The measures utilized shall be
subject to the approval of the Authority.
5.
Any exceedance of a CAMP threshold or action level
shall be reported to the NYCSCA IEH Division
immediately and additionally in writing within 2
hours of the time it is recorded.
The report
shall include the instrument readings, location of
the monitoring station where the exceedance was
recorded, readings at upwind locations, duration
of elevated readings (i.e., number of 15 minute
EARTHWORK 02200 - 30
12/05/14
DESIGN No. _____
time-weighted exceedances),
activities being
performed at the time of the exceedances, and
descriptions of countermeasures implemented to
control
the
exceedance
and
prevent
future
occurrences.
6.
A qualified environmental monitor with “stop work
authority” shall be responsible for the air
monitoring and daily calibration and maintenance
of
the
equipment
in
accordance
with
the
manufacturer’s specifications. The resume of the
proposed qualified environmental monitor shall be
included in the Contractor prepared CAMP for IEH
review and approval. Copies of manufacturers’
owner’s manuals for instrumentation to be used
shall
be
included
in
the
CAMP.
All
instrumentation and equipment shall be maintained
at all times in proper operating condition.
7.
The qualified environmental monitor shall document
in the dedicated project log book each calibration
event, any equipment and instrument malfunctions,
unusual
conditions,
air
monitoring
station
locations, any exceedances of action levels and
countermeasures implemented. Dates and times must
be well documented.
8.
The Contractor shall respond to exceedances of the
CAMP action levels immediately.
3.03 EXCAVATION - GENERAL
13 A.
Excavate all materials of every kind to the Contract
elevations and dimensions required by the Drawings and
Specifications and any additional material required for
safe slope of excavation, regardless of the character
of materials and obstructions encountered.
Prior to
excavation, perform GPR survey of area of excavation to
determine location of any unknown buried utilities.
B.
No
additional
compensation
will
be
allowed
for
excavation or foundation work carried below the levels
shown on Drawings unless same has been authorized in
writing by the Authority.
Contractor is responsible
for all remedial work due to unauthorized excavation.
C.
Level off and grade bottoms of excavations to receive
footings, foundations, floors, etc.
D.
For footings and foundations, machine excavation is
allowed to within one foot of final subgrade. Excavate
balance by hand.
Excavate to a tolerance of plus or
minus 0.10' and extend a sufficient distance from the
structures to permit placing and removal of formwork,
installation of services, other construction, and for
inspection.
NYCSCA
EARTHWORK 02200 - 31
12/05/14
DESIGN No. _____
E.
For pavements and slabs on grade, excavate to depths
required for installation of aggregate base or pavement
as specified herein or shown on Drawings.
F.
Excavation of pile caps is Work of this Section and is
described in Section 02360.
G.
All excavations for foundations and footings must be
completed and the underlying soil or rock material
approved by the Special Inspector before concrete
foundation work is started.
The Contractor may, with
the written approval of the Authority, proceed with
concrete foundation work before the entire building
excavation has been completed. In addition, excavation
for foundations and footings shall conform to Section
BC 3304 unless more severe requirements are given in
this Section.
H.
Remove all excavated material from the site and legally
dispose of away from the premises in accordance with
the requirements specified in this section. Burning of
material on the site is not permitted.
I.
Trenching for pipes and conduits is described under
"Excavation of Trenches."
J.
Exposed Ground Surfaces/Landscaped Areas:
1.
At seeded, sodded, or ground cover areas, excavate
to 24" below finished grade.
If rock occurs
within 18" of finished grade, all rock shall be
removed to a depth of 18". Where existing stone,
concrete, brick, or other masonry occurs at these
areas, such material shall be excavated and
removed to a minimum depth of 24" from finished
grade.
2.
In garden areas or where shrubbery/trees are
required, including tree pits, excavate to 24"
below finished grade, but if rock occurs within
36" of finished grade, all rock to a depth of 36"
shall be removed. Where existing stone, concrete,
brick, or other masonry occurs at these areas,
such material shall be excavated and removed to a
minimum depth of 24" from finished grade.
3.
For additional excavation requirements of tree
pits below the general excavation levels called
for under this article, refer to Section 02900.
3.04 EXCAVATION - ROCK
A.
NYCSCA
Excavate rock where encountered by blasting or other
means necessary.
EARTHWORK 02200 - 32
12/05/14
DESIGN No. _____
B.
Excavation by blasting shall be permitted only when
specifically approved by the Authority and by all
authorities
having
jurisdiction,
including
the
Explosive Unit of the Bureau of Fire Prevention of the
New York City Fire Department.
All irregularities of
surface on lines of walls, or under columns, piers or
footings shall be carefully examined and all loose or
shaken rock shall be removed down to a solid horizontal
bearing surface.
C.
Blasting shall be done by persons skilled in such work.
Exercise care in the handling and storing of dynamite
and other explosives as he shall be held responsible
for any injury to persons or damage to property which
may occur as a result of premature explosions, overcharges of explosives, failure to provide proper
coverings, or the omission of any precautions in
connection with the performance of the work that is
required by the NYC Building Code or other city bureaus
having jurisdiction over this Work.
D.
Place monitoring devices on all buildings adjacent to
the site and as directed by governing authorities to
ensure damage to property does not occur.
Halt
operations if damage is noted or if blasting limits set
by the Fire Department are exceeded.
Perform all
remedial work required due to blasting.
3.05 EXCAVATION OF TRENCHES
A.
NYCSCA
General
1.
Trenching for trench drains, pipes, and conduits
shall
be
accomplished
with
an
appropriate
trenching machine, except hand trenching shall be
used where machine may damage existing underground
pipe, conduit, or other objects to remain.
2.
Excavate
trenches
to
elevations required
install pipes and conduits at required inverts,
required by governing regulatory agencies,
shown on Drawings, as specified herein, and
allow encasement in concrete when indicated
Drawings.
3.
Remove
loose
material
and
proofroll
trench
subgrade with a vibratory plate or jumping
compactor (a minimum of 6 passes, 3 in each
direction, if material is fill) in the presence of
the Special Inspector. Remove any soft spots and
replace with controlled fill, compacting material
in 4" lifts to 92% (95% in vehicular areas) of
maximum dry density by ASTM D1557 at optimum
moisture content.
to
as
as
to
on
EARTHWORK 02200 - 33
12/05/14
B.
C.
NYCSCA
DESIGN No. _____
4.
Prevent trench bottoms from freezing until items
are placed and the trench backfilled.
5.
Fill trench with concrete to a depth even with the
bottom of footings when excavations pass within
18" of the footings at a depth below the footing.
Continue concrete 2'-0" each side of the footing.
6.
Work outside the street line is governed by the
regulatory authority having jurisdiction for such.
7.
Coordinate locations and excavation
work of Divisions 15 and 16.
depths
with
Sectional Trench Drains
1.
Excavate trench to width and depth sufficient to
provide for concrete cover as indicated on
Drawings and to permit workmen to properly install
the sectional trench drain.
2.
Carefully construct and grade the bottom of the
trench to approximate the slope of the bottom of
the trench drain.
The drain bottom shall have
solid bearing along its entire length and be true
to line and grade when completed.
3.
Slope the edges of the excavations as required to
provide a smooth transition to the slab or asphalt
subgrade.
4.
Make excavations about the centerline of all the
proposed drainage runs.
5.
Prepare deeper excavations for the catch basins.
6.
Compact
above.
7.
Trenches shall be dry when trench bottom
prepared and when bedding concrete is placed.
subgrade
as
indicated
in
paragraph
A
is
Piping (Drainage, water, oil, gas, etc.)
1.
Excavate trenches to depths required and to width
sufficient to permit workmen to properly install
the pipe, but in no case shall there be less than
6" clearance on each side of the pipe.
2.
Carefully grade and construct the bottom of the
trenches so that the pipe between the joints shall
have solid bearing along its entire length and be
true to line and grade when in final position.
EARTHWORK 02200 - 34
12/05/14
D.
DESIGN No. _____
a.
Where concrete encasement is required
Drawings,
provide
sufficient
depth
accommodate concrete.
b.
Where trench bottom is rock, provide an
additional 6" of depth to allow for sand
cushion.
subgrade
as
indicated
in
paragraph
by
to
3.
Compact
above.
A
4.
The bottom of the trenches, where required, shall
be hollowed for each hub (bell holes) to provide
full-length barrel support of the pipe and to
prevent loading at the bells.
5.
Keep trenches dry during pipe laying.
At water
pipe, line trenches with non-woven geotextile
filter fabric immediately before pipe laying to
prevent soil contamination in the pipe.
Conduits
1.
Excavate trenches to depths required and to width
sufficient to permit workmen to properly install
the conduit, but in no case shall there be less
than 3" clearance on each side of the conduit.
The depth shall not be less than that required to
leave a space of not less than 20" between the
highest point of the conduits and the finished
grade.
2.
Carefully grade and construct the bottom of
trenches so that the conduits shall have solid
bearing along their entire length and be true to
line and grade when in final position.
3.
Compact
above.
4.
Keep trenches dry during conduit laying.
subgrade
as
indicated
in
paragraph
A
3.06 DISPOSAL OF EXCAVATED MATERIAL
A.
Description of Work
1.
NYCSCA
Deliver material excavated from the site to an
approved off-site disposal facility identified in
the Excavated Material Disposal Plan.
The
Excavated Material Disposal Plan must be prepared
in accordance with paragraph B of this article and
must be and approved by the Authority’s Industrial
and Environmental Hygiene Division (IEH) prior to
the start of excavation. No claims of delay shall
be permitted due to the Contractor’s failure to
obtain approval of the Excavated Material Disposal
EARTHWORK 02200 - 35
12/05/14
DESIGN No. _____
Plan from the IEH Division. All required sampling
and testing are part of the Work and are to be
done by the Contractor as part of this project at
no additional cost to the Authority. The resulting
sampling data is to be submitted to the Authority
as an addendum to the Excavated Material Disposal
Plan.
19
B.
2.
Non-Hazardous Excavated Material, as defined in
Paragraph 1.05C, that has been excavated as part
of the construction project, shall be transported
to an off-site disposal facility meeting the
requirements of 6 NYCRR Part 360 or equivalent
out-of-state facility approved by the appropriate
regulatory agency of that State with a permit to
receive non-hazardous excavated material. All
petroleum-contaminated material, as defined in
Paragraph
1.05D,
if
discovered,
shall
be
transported to an off-site disposal facility
permitted
to
receive
petroleum-contaminated
material from known source areas.
All hazardous
waste,
as
defined
in
Paragraph
1.05E,
if
discovered, shall be transported to an off-site
disposal facility meeting the requirements of 40
CFR Part 265 and 6 NYCRR Part 373 or equivalent
out-of-state facility approved by the appropriate
regulatory agency of that State with a permit to
receive hazardous waste.
Excavated Material Disposal Plan
An Excavated Material Disposal Plan shall be prepared
by the Contractor and approved by NYCSCA IEH for nonhazardous excavated material at a minimum of four weeks
prior to the start of excavation. A separate Excavated
Material Disposal Plan for any additional categories of
material, as defined in Paragraphs 1.05D and E,
encountered during the excavation, shall be prepared by
the Contractor and approved by NYCSCA IEH prior to
removing the material off-site. The Excavated Material
Disposal Plan shall be prepared and signed by a
Certified Hazardous Materials Manager approved by the
Institute
of
Hazardous
Materials
Management
in
Rockville,
Maryland,
or
Qualified
Environmental
Professional, approved by the Institute of Professional
Environmental Practice, Pittsburgh, Pennsylvania, or
similar board-certified professions. The Excavated
Material Disposal Plan shall be prepared in accordance
with the IEH Division template attached to this
Section.
The Contractor shall strictly adhere to the
format and content guidance of the IEH Division
template. In the Excavated Material Disposal Plan, the
Contractor shall, at a minimum:
1.
NYCSCA
Indicate how buried utilities (e.g. electric, gas,
water, sewers, telephone, etc.) will be located
EARTHWORK 02200 - 36
12/05/14
DESIGN No. _____
and provide copies of the resulting information to
the Authority.
NYCSCA
2.
Confirm appropriate contact will be made with
underground facilities protective organizations –
in
accordance
with
applicable
laws
and
regulations.
3.
Provide
a
to-scale
figure
indicating
the
quantities of excavated material and proposed
locations where discrete soil samples shall be
collected and which discrete soil samples shall
make up each composite sample.
4.
Define the acceptance and waste characterization
requirements of each proposed disposal facility
and define the sampling rates (e.g., one composite
sample / 500 cubic yards) along with the estimated
quantity of material to be disposed for each
proposed disposal facility.
5.
Define
the
sampling
methods
(e.g.
Geoprobe®, drill rig, etc.) to be used.
6.
Define the analytical parameters
methods for analyzing all samples.
7.
Define how chain-of-custody will be maintained and
recorded.
8.
Define how the QA/QC of the Excavated Material
Disposal Plan will be maintained and how it will
be subject to audit by both the Authority and the
Contractor.
9.
Provide a listing, including company name, name of
owner, and address of facility, of the off-site
disposal facility(ies) meeting the requirements
listed in Item A above, for the specific material
to be disposed and a copy of each facility’s
permit (NYSDEC and/or equivalent out of state) and
a
complete
listing
of
the
facility’s
preacceptance testing and disposal requirements for
the specific material.
10.
Health and Safety Plan for handling the material
to be excavated.
11.
Provide a listing, including company name and
address, of proposed waste haulers.
Provide for
each proposed waste hauler a copy of the valid 6
NYCRR 364 Waste Transporter Permit.
Contractor
shall furnish a list approved by the Authority
that identifies the make, model, truck number and
registration plate number of each of the trucks
that
shall
transport
the
material
to
the
and
backhoe,
analytical
EARTHWORK 02200 - 37
12/05/14
DESIGN No. _____
designated
facility(ies).
All
proposed
destination facilities, listed as required by 9
above, shall be listed in the waste transporter
permits provided.
12.
If applicable, provide a completed waste profile
form for the proposed facility(ies) along with a
cover letter on Contractor letterhead certifying
that the Contractor has provided the disposal
facility with the analytical data.
Contractor
must verify in writing that full disclosure of
soil characterization has been provided to the
disposal facility.
C.
Material Suitability and Construction Methods:
18
1.
All material excavated from the site shall be
transported by the Contractor to an approved offsite designated facility.
Environmentally clean
material meeting controlled fill gradation may be
reused pending credit to the Authority. When the
Authority orders the Contractor to excavate during
other than normal construction hours, the material
shall be stockpiled on the site until the material
can be delivered to the facility identified in the
approved
Excavated
Material
Disposal
Plan.
Stockpiled excavated soil shall be covered with
heavy duty tarps, secured with sand bags.
If
there is no room on the site for stockpiling,
provide containers for stockpiling or other means.
2.
Provide
all
labor,
equipment
and
material
necessary to excavate, stockpile, load, handle,
and transport excavated material from the site to
the facility(ies) designated in the approved
Excavated Material Disposal Plan, as described
herein, and conditioned on the following:
NYCSCA
a.
Comply with all rules and regulations of the
body governing the facility(ies) listed in
the approved Excavated Material Disposal
Plan.
b.
Any
sorting
of
the
excavated
material
required by the designated facility(ies) is
part of the Work and is the responsibility of
the Contractor.
c.
Prior to commencing off-site disposal, the
Contractor shall furnish a list approved by
the Authority that identifies the make,
model, truck number and registration plate
number of each of the trucks that shall
transport the material to the designated
facility(ies)
defined
in
the
Excavated
Material Disposal Plan.
Any change of
EARTHWORK 02200 - 38
12/05/14
DESIGN No. _____
trucks, or additional trucks, shall have
prior approval at least 24 hours in advance.
The Contractor shall also furnish a list,
approved by the Authority, of the water-level
volume of each truck, regardless of whether
or not the truck possesses a DOT truck permit
number indicating truck volume.
D.
d.
The Contractor agrees and warrants that each
load of such material has originated only
from the Project Site described in this
Project and has not been mixed with material
from any other site.
e.
On a daily basis the Contractor shall provide
originals
of
all
dump
tickets
to
the
Authority.
Excavated Material
1.
The excavated material may consist of one or more
of
the
following:
non-hazardous
excavated
material, petroleum-contaminated material and/or
hazardous wastes.
For the purpose of the base
bid, the Contractor shall assume that all material
excavated from the site meets the definition of
non-hazardous excavated material, and will exceed
6 NYCRR 375-6 Unrestricted Use and Restricted Use
Soil Cleanup Objectives and NYSDEC CP-51: Soil
Cleanup
Guidance
Supplemental
Soil
Cleanup
Objectives.
2.
All excavated material from the site shall
disposed of in one of the following manners.
19
a.
In accordance with the approved Excavated
Material Disposal Plan developed for this
specific
material,
the
Contractor
shall
transport and dispose of all non-hazardous
excavated material at an approved permitted
off-site
disposal
facility
meeting
the
requirements
of
6
NYCRR
Part
360
or
equivalent
out-of-state
requirements.
If
material is temporarily stockpiled on-site,
the stockpile shall be covered and silt curbs
shall be installed around the stockpile.
b.
If required and directed by the Authority,
the Contractor shall stockpile or stage
petroleum-contaminated material, as defined
in 1.05D, at the site pending sample analysis
and off-site disposal.
The stockpile shall
be covered and silt curbs shall be installed
around the stockpile.
The Contractor shall
negotiate with an approved off-site disposal
facility
licensed
to
receive
petroleum-
18
18
NYCSCA
be
EARTHWORK 02200 - 39
12/05/14
DESIGN No. _____
contaminated material. The Contractor shall
provide the NYCSCA with a copy of the offsite disposal facility’s permit to receive
petroleum-contaminated material as part of
the separate Excavated Material Disposal
Plan. Prior to disposal of this material, the
Contractor shall obtain written authorization
from
the
Authority.
In
addition
the
Contractor shall provide the Authority with
original copies of all shipping papers
including
manifests,
weigh
tickets,
and
original invoices for the disposal of this
material.
The Contractor shall comply with
all applicable federal, state, and local
rules and regulations pertaining to the
handling,
management,
loading,
transportation, and disposal of petroleumcontaminated material.
c.
18
3.
The Contractor shall provide all labor, equipment
and material necessary to excavate, load, handle,
and transport excavated material, as described
herein,
from
the
site
to
the
designated
facility(ies),
and
in
accordance
with
the
following:
a.
NYCSCA
If required and directed by the Authority,
the Contractor shall stockpile or stage
hazardous waste, as defined in Paragraph
1.05E at the site pending sample analysis and
off-site disposal.
The stockpile shall be
covered and silt curbs shall be installed
around the stockpile. The Contractor shall
provide the NYCSCA with a copy of the offsite disposal facility’s permit to receive
hazardous waste as part of the separate
Excavated Material Disposal Plan. Prior to
disposal of this material, the Contractor
shall obtain written authorization from the
Authority. In addition the Contractor shall
provide the Authority with original copies of
all shipping papers including manifests,
weigh tickets, and original invoices for the
disposal of this material. The Contractor
shall negotiate with an approved off-site
disposal facility meeting the requirements of
40 CFR 265 and licensed to receive hazardous
wastes. The Contractor shall comply with all
applicable federal, state, and local rules
and regulations pertaining to the handling,
management,
loading,
transportation,
and
disposal of hazardous waste.
The
Contractor
shall
comply
with
all
applicable federal, state, and local rules
and regulations pertaining to the disposal of
EARTHWORK 02200 - 40
12/05/14
DESIGN No. _____
non-hazardous excavated material, and, if
applicable, petroleum-contaminated material,
and hazardous waste.
NYCSCA
b.
The Contractor shall
use and identify, in
the Excavated Material Disposal Plan, only
properly
licensed
and
insured
off-site
disposal facilities that can accept nonhazardous
excavated
material,
and,
if
applicable, petroleum-contaminated material
and/or hazardous waste.
c.
Prior to commencing off-site disposal, the
Contractor shall furnish to the Authority a
list
approved
by
the
Authority
that
identifies the make, model, truck number and
registration plate number of each of the
trucks that will transport the material to
the off-site facilities.
Any change of
trucks, or additional trucks, shall require
prior approval at least 24 hours in advance.
The Contractor shall also furnish to the
Authority a list, approved by the Authority,
of the water-level volume of each truck,
regardless of whether the truck possesses a
DOT truck permit number indicating truck
volume.
4.
The Contractor is responsible for implementing all
appropriate dust and/or odor control measures,
including, but not limited to, water suppression.
5.
Prior to departure from the site, transport
vehicles shipping excavated material shall be
inspected and cleaned as necessary to prevent
tracking material off-site.
Contractor shall
properly collect and properly dispose, at an
Authority-approved facility, all waste generated
from cleaning.
6.
The
Contractor
shall
provide
all
required
notifications to federal, state and local agencies
prior to transporting material off site.
Copies
of all notifications issued shall be transmitted
to the Authority at the time of issuance.
7.
The Contractor shall screen drivers of transport
vehicles
prior
to
engagement
and
prior
to
departure from the site. Vehicle drivers shall be
fully-licensed and possess appropriate training.
8.
Vehicles used to transport excavated material
shall
be
designed,
equipped,
operated
and
maintained
to
prevent
leakage, spillage and
airborne emissions during transport. Only safe,
suitable and well-maintained vehicles, which are
EARTHWORK 02200 - 41
12/05/14
DESIGN No. _____
properly labeled/placarded, manned, permitted and
registered to perform the required transportation
services, shall be used.
19
10
E.
Payment
1.
All labor, materials, equipment, and incidentals
to perform all work under this Section shall be
included in the base bid. No separate payment will
be made for any Work associated with the disposal
of non-hazardous excavated material, as the cost
of said work shall be deemed included in the
Contract.
2.
Reimbursement
of
payment
for
transport
and
disposal of any petroleum-contaminated material
and hazardous waste encountered, and approved by
the Authority, shall be reimbursed at negotiated
unit
rates,
exclusive
of quantities already
provided for elsewhere in the documents that shall
be included in the base bid.
3.
Payment for the transportation and disposal of
petroleum-contaminated
material
and
hazardous
waste encountered not part of the base bid shall
be contingent upon the Authority’s receipt of
original shipping documents (e.g., manifests),
weigh
tickets,
and
original
invoices.
No
additional
payment
will
be
made
for
excavating/removing
and
loading
and
other
requirements of this Section for these materials
because it is covered under the base bid.
4.
The Contractor shall credit the Authority for any
quantities
of
excavated
material
that
the
Authority approves for reuse on-site.
3.07 FILLING AND GRADING
A.
NYCSCA
General
1.
Do not commence filling and backfilling operations
until proposed fill and backfill have been
approved by the IEH Division (in addition to
gradation approvals), construction below finish
grade has been approved, underground utilities and
mechanical items inspected and tested, forms
removed,
waterproofing/membranes/coatings
and
other improvements installed, trash and debris
removed, and temporary and permanent bracing
installed.
2.
Do not commence backfilling, filling and grading
until existing subgrades have been compacted.
EARTHWORK 02200 - 42
12/05/14
B.
DESIGN No. _____
3.
Backfilling
of
trenches
"Backfilling of Trenches".
is
described
under
4.
Fill all excavations, backfill against all walls,
and do all filling and grading necessary to bring
the surfaces to the level required.
5.
Do not backfill against concrete elements until
the
concrete
has
obtained
its
specified
compressive strength.
6.
Perform backfilling around foundation walls when
in the opinion of the Engineer of Record floor
beams
and/or
concrete
slabs form sufficient
bracing to withstand the backfill pressure.
All
other fill, backfill, and rolling to approximately
finished grades shall then be completed.
7.
Take particular care when rolling over areas where
trenches or other excavations have been made and
backfilled.
8.
Fill voids caused by the removal of below grade
improvements.
9.
Grade bottoms of pavements and area way bottoms
toward sediment pits or catch basins to maintain
uniform thickness of the slabs.
10.
A minimum of twenty-four 24” of environmentally
clean fill (as defined in paragraph 1.05F) that
has been tested utilizing laboratory reporting
limits which are acceptable to the Authority
(i.e., below the regulatory comparison criteria)
shall be used on all exposed ground surfaces,
including
landscaped
areas
(grass,
sod,
groundcover, shrub areas, tree areas, including
tree pits, etc).
Provide environmentally clean
fill to bring soil to depth below the required
amount of top soil required for each type of
planting as described in Section 02900.
Compaction of existing subgrade
1.
Site preparation
Existing subgrade shall be free from stumps,
bushes, roots, sod, topsoil, rubbish, garbage, and
any other material that may decay.
2.
Grading
a.
NYCSCA
Prior to placing fill or backfill in any
area, grading is to be performed as required
to provide for drainage. Ditching or filling
around the area shall be performed to
EARTHWORK 02200 - 43
12/05/14
DESIGN No. _____
intercept or divert all surface water.
Within the area, the ground in which fill is
to be placed shall be graded so as to provide
for unobstructed drainage from every point to
a sump or other disposal point.
6
3.
b.
On completion of grading as specified above,
closely
examine
to
determine
whether
excessive wetness, springs, or other seepage
of water can be observed at any point.
If
such conditions exist, positive drainage in
suitable form, such as french drains or
tilling, must be provided before placement of
fill is undertaken.
c.
When the fill area has been prepared as
specified above, compact the natural ground
surface by methods indicated in 3 below.
Method of Compaction
a.
Natural undisturbed material shall be graded
and compacted to attain a uniform surface.
These areas shall be determined by the
Special Inspector.
b.
Existing subgrade shall be proofrolled in the
presence of the Special Inspector for the
following conditions:
c.
4.
NYCSCA
1)
Subgrade consists of uncontrolled fills.
2)
Identification of shallow loose zones of
material
or
identification
of
soft/spongy material at surface.
Proofrolling shall be accomplished with a
minimum of four passes using a compactor of
minimum static weight of 19,000 lbs, a
minimum dynamic force of 40,000 lbs, and a
total applied force of not less than 7,500
per
foot
of
drum
width.
In
areas
inaccessible to the heavy equipment, provide
a minimum of six passes with a vibratory
plate or jumping compactor.
Fill shall not
be placed until the subgrade is approved by
the Special Inspector.
Soft Areas During Compaction: If any areas show
pumping,
noticeable
weaving,
or
which
are
otherwise unsatisfactory, undercut material within
the limits and extent ordered by the Special
Inspector.
These areas shall be replaced with
controlled
fill,
compacted
to
92%
(95%
in
vehicular areas) of maximum dry density by ASTM
EARTHWORK 02200 - 44
12/05/14
DESIGN No. _____
D1557
at
optimum
moisture
content,
unless
otherwise directed by the Engineer of Record.
11
C.
Placement and Compaction of Fill and Backfill
1.
2.
Placement
a.
General:
Begin fill and backfilling in the
lowest section of the area. Spread material
evenly by mechanical equipment or by manual
means above the approved compacted subgrade
in lifts not exceeding 6" to 8" for material
compacted by heavy machinery and 4" for
material compacted by hand tamping.
Build
layers as horizontally as practical to
prevent thickness of lift from exceeding that
specified
but
provide
with
sufficient
longitudinal and transverse slope to provide
for runoff of surface water from every point.
b.
Moisture Control: The moisture-density curve
for the fill use shall be supplied to the
Contractor as a guide in controlling moisture
to achieve the required degree of compaction.
If, in the opinion of the Special Inspector,
fill material becomes too wet for the
required compaction, the fill shall be dried
by a method approved by the Special Inspector
prior to commencing or continuing compaction
operations. Likewise, if, in the opinion of
the Special Inspector, the fill material
becomes too dry for the required compaction,
the fill shall be moistened by a method
approved by the Special Inspector prior to
commencing
or
continuing
compaction
operations.
Compaction:
Compact each lift to the degree of
compaction indicated below.
The degree of
compaction shall be checked by the Special
Inspector and each successive lift shall not be
placed or compacted until the previous lift is
inspected and approved by the Special Inspector.
Compact the fill and backfill to elevations and
limits shown on Drawings and is subject to final
inspection and approval by the Special Inspector.
Extend the compacted fill beyond the berm lines on
a slope downward at a maximum slope of two
horizontal to one vertical to intersect the
approved stripped subgrade.
Maintain the fill
slopes at all times.
a.
NYCSCA
Areas to receive heavy vehicular traffic: 95%
of the maximum dry laboratory density by
D1557 at optimum moisture content.
EARTHWORK 02200 - 45
12/05/14
DESIGN No. _____
5
22
D.
All other areas: 92% of the
laboratory density by D1557.
maximum
dry
3.
Drainage During Fill Operation:
At all times,
maintain and operate proper and adequate surface
and subsurface drainage to the satisfaction of the
Special
Inspector
in
order
to
keep
the
construction site dry and in such condition that
placement and compaction of fill may proceed
unhindered by saturation of the area.
Submit
method of dewatering to the Authority for prior
approval.
Such approval shall not relieve the
Contractor of his responsibility to maintain the
site dry during the compaction operation.
See
Article 3.02.
4.
Frost:
Do not place fill materials when either
the fill materials or the previous lift (or
subgrade) on which it is placed is frozen. In the
event that any fill which has already been placed
on the surface shall become frozen, it shall be
scarified and recompacted, or removed, to the
approval of the Special Inspector before the next
lift is placed.
Remove or recompact any soft
spots resulting from frost to the satisfaction of
the Special Inspector before new fill is placed.
Placement and Compaction of Aggregate Bases, Gas
Permeable Aggregate, Crushed Stone, and Broken Stone
Ballast
1.
Provide
pavements
Drawings
stone/gas
slabs.
otherwise
2.
Verify finished subgrade is at proper level.
3.
Prior to placement of material, reroll subgrade
with a two-ton roller or hand tamper.
4.
Place aggregate base, crushed stone, and gas
permeable
aggregate
in
layers
of
uniform
thickness, but not exceeding 6". Compact material
to either 80% of relative density or 92% (95% for
heavy vehicular traffic areas) of maximum dry
density at optimum moisture in accordance with
ASTM D1557. For gas permeable aggregate, provide
proofrolling
using
multiple
passes
of
the
compactor to prevent shoving of the material.
Maintain optimum moisture content for compacting
the material. Place material in single layer for
aggregate courses 6” or less.
Alternate blading
25
NYCSCA
b.
aggregate
base
under
all
exterior
and wherever else indicated on the
or specified herein.
Provide crushed
permeable aggregate under all interior
Provide 6" minimum unless specified
elsewhere.
EARTHWORK 02200 - 46
12/05/14
DESIGN No. _____
and rolling to obtain a
uniformly compacted course.
smooth,
even,
and
3.08 BACKFILLING OF TRENCHES
A.
General
1.
Do
not
backfill
trenches
until
tests
and
inspections have been made and the backfilling
authorized by the Authority.
Use care to avoid
damage or displacement of pipe or conduit.
2.
Backfill with controlled fill and compact each
layer to 92% (95% for vehicular areas) of its
maximum density as per ASTM D1557 using a
vibratory plates, jumping compactors, or other
approved means.
12
5
B.
C.
NYCSCA
Piping
1.
Backfill piping immediately after piping lines are
tested
and
inspected
and
approved
by
representatives of the Department of Building,
other regulatory agencies having jurisdiction, and
the Authority.
2.
For piping and trench drains encased in concrete,
backfill immediately after concrete has attained
its required strength and after inspection and
approval by the Authority.
3.
Backfill trenches by hand and place in uniform
layers not exceeding 4" in depth up to a level of
one foot over the crown of the pipe and/or
sectional trench drain invert.
Each layer shall
be placed and then carefully and uniformly tamped,
using a hand tamper in such a manner as to avoid
injury and displacement of the pipe and/or
sectional trench drain.
4.
Backfill the remaining height of the trench as
previously specified, except that the layers shall
be uniformly compacted using a mechanical vibrator
tamper.
Limit the addition of water during
backfilling to provide optimum moisture content
for tamping procedures.
Conduits
1.
Backfill trenches immediately after conduit pipes
are laid therein, inspected, and approved by the
Authority.
2.
Backfill trench by hand and place in uniform
layers not exceeding 4" in depth to a level of one
foot above the top of the conduits.
Each layer
EARTHWORK 02200 - 47
12/05/14
DESIGN No. _____
shall be placed and then carefully and uniformly
tamped, using a hand tamper in such manner to
avoid injury and displacement of the conduits.
3.
Backfill the remaining height of the trench as
previously specified, except that the layers shall
be uniformly compacted using a mechanical vibrator
tamper.
Limit the addition of water during
backfilling to provide optimum moisture content
for tamping procedures.
3.09 FIELD QUALITY CONTROL
A.
15
Tests
1.
Sieve Analysis:
The Authority's Laboratory will
perform sieve analysis in accordance with ASTM
D422 on fill and aggregate materials at the site
prior to placement in order to verify conformance
with the submitted samples.
The laboratory will
take one sample at a minimum for every 100 CY
placed (or portion thereof) each day. If material
appears to vary from approved material, more
frequent testing will be done and if results
indicate material varies from that approved, costs
of such testing will paid by the Contractor.
2.
Field density tests: The Authority's Laboratory
will perform in-place field density tests in
accordance with either of the three following
procedures; ASTM D1556, ASTM D2167, or ASTM D2922.
3.
a.
Existing subgrade.
One field density test
for each 2000 ft2, but in no case less than
three tests.
b.
Fill areas - For each lift, one field density
test for each 2000 ft2, but in no case less
than three tests.
c.
Backfill areas - For each area, two field
density
tests
per
lift
at
locations
determined by Special Inspector and one test
per lift for every 50 linear feet of trench.
Load Bearing Tests
If required, the Authority's testing laboratory
will perform load bearing tests to determine the
soil bearing capacity where suspect.
Provide
access to site and cooperate with the Authority's
testing laboratory in completing the load bearing
tests.
NYCSCA
EARTHWORK 02200 - 48
12/05/14
DESIGN No. _____
4.
5.
Environmentally Clean Fill/Backfill Tests
a.
The
Authority,
as
a
quality
assurance
measure, may perform applicable analysis of
fill/backfill material samples to verify that
the material meets the environmentally clean
fill requirements.
b.
The Contractor shall notify the IEH Division
of the Authority a minimum of two business
days prior to collection for environmental
testing of each sample of environmentally
clean
fill,
and,
if
requested
by
the
Authority, shall arrange for a representative
of the IEH Division to observe collection of
each sample.
c.
The
Authority
will
require
that
the
Contractor
provide
the
certifications
required by this specification at the time of
delivery
of
each
and
every
load
of
environmentally clean fill showing that the
load was shipped to the site directly from
the approved source of environmentally clean
fill.
d.
The
Contractor
shall
be
required
when
requested by the Authority to arrange for
access for a representative of the Authority
to observe the loading of trucks at the
source of environmentally clean fill.
Test Borings
The Authority, at its discretion, may take
additional test borings.
The Contractor shall
provide access to site and cooperate with the
Authority's boring contractor in completing the
borings.
B.
NYCSCA
Inspection
1.
Fill and Backfill Compaction:
The Special
Inspector will give approval for each lift in
accordance
with
Sections
BC
1704.7.2
and
BC 1704.7.3.
In the event that the compaction
requirements are not satisfied, the lift shall be
rerolled or removed and again tested until the
required compaction is obtained.
2.
Footing Subgrade:
The Special Inspector is
responsible for approval of bearing capacity for
all
footings
in
accordance
with
Section
BC 1704.7.1.
EARTHWORK 02200 - 49
12/05/14
C.
DESIGN No. _____
3.
Underpinning:
The
Special
Inspector
is
responsible for inspection of underpinning in
accordance
with
Section
BC 1704.20.3.
Contractor’s licensed professional engineer is to
file all design documents as specified in Article
3.02 of this Section.
4.
Excavation - Sheeting, Shoring, and Bracing: The
Special Inspector is responsible for inspection of
underpinning
in
accordance
with Sections BC
1704.20.2 and BC 3304.4.1.
Contractor’s licensed
professional engineer is to file all design
documents as specified in Article 3.02 of this
Section.
5.
Contractor's Responsibility: The Contractor shall
notify the Authority at least 48 hours prior to
filling operations, pouring of footings, and
installation
of
underpinning
and
excavation
support to allow for the Authority to have the
appropriate personnel at the site.
6.
Contractor’s Inspections: Inspections and testing
performed by the Authority shall not relieve the
Contractor of responsibility for performing all
other testing and inspection specified herein or
otherwise necessary to meet the quality control
and
quality
assurance
requirements
of
this
Section.
Responsibility
1.
All
required
testing
and/or
analysis
not
specifically defined as being provided by the
Authority shall be provided by the Contractor as
part of the included Work and costs of this
Project.
2.
No testing and/or analysis by the Authority shall
relieve the Contractor of the responsibility of
conforming
to
the
requirements
of
these
specifications.
3.
Time for conducting the tests and/or inspections
defined
in
these
specifications
shall
be
considered as part of the Work of this Project and
neither extension of time nor additional costs
shall be accepted as a result.
3.10 PROTECTION
A.
NYCSCA
Protect graded and compacted areas from traffic and
erosion. Keep free of trash and debris.
EARTHWORK 02200 - 50
12/05/14
DESIGN No. _____
B.
When completed compacted areas are disturbed by
subsequent construction or weather, scarify surface,
re-shape, and compact to required density prior to
further construction.
C.
Where settling is measurable or observable at excavated
areas during general project warranty period, remove
surface (pavement, lawn or other finish), add backfill
material, compact, and replace surface treatment.
Restore appearance, quality, and condition of surface
or finish to match adjacent work, and eliminate
evidence of restoration to greatest extent possible.
D.
A guardrail or solid enclosure at least 3’-6” high
shall be provided along the open sides of excavations,
except if the side slopes are one vertical to three
horizontal or flatter.
END OF SECTION
Notes to Specifier (Delete from Specification)
1.
Use Section 02200A if Project includes a 'Vertical Drain'
athletic field. Use Section 02200B if Project includes a
'Float Drain' athletic field or if Project includes a grass
athletic field and modify to suit. Decide for any field or
playground how much soil needs to the excavated. It may be
easier to use 02201 or 02200B if project is just a
playground.
2.
The IEH unit will provide appropriate modifications to this
section if Asbestos containing, Petroleum containing, or
hazardous waste material is found.
3.
Delete Sections that don’t apply and add additional Sections
provided by IEH for required remediation.
4.
If
Environmental
Investigations
have
identified
contamination, add relevant information in Article 1.01C and
insert reference to Section 02010, as well as other related
sections, in Article 1.02.
If asbestos survey did not
identify asbestos contaminated soil or debris, delete Article
1.01C.
5.
Placing of footings on controlled fill shall be avoided and
is to be reviewed by the SCA.
If controlled fill is used
under
footings
or
heavy
traffic
areas,
verify with
geotechnical
engineer
any
special
provisions
to
the
specification.
If footings are to be placed on fill,
compaction to 95% of laboratory density by ASTM D1557 as per
Building Code shall be indicated in all locations of
specifications where compaction requirements are listed.
6.
Verify type of compaction required for different subgrade
conditions.
Heavy proofrolling is adequate for most fills
NYCSCA
EARTHWORK 02200 - 51
12/05/14
DESIGN No. _____
and sands, but sensitive material such as clays and silts
require special procedures.
7.
'Broken Stone Ballast' is sometimes used under certain types
of footings where bearing capacity is in question or to
stabilize a wet subgrade.
Verify with Engineer if it is
needed or not.
8.
Not used.
9.
Not used.
10.
Specify installation of geotextiles if required (Already
specified in 02512 for 'Vertical Drain' fields). Add to list
of product data and samples.
11.
If drainage panel or exterior waterproofing is required,
refer to those Sections for any special backfilling
requirements.
12.
Make sure sand cushion mentioned under trench excavation is
accounted for. If poor soil is on the site, provide 6" of
controlled fill under pipe or concrete encasement or cradle.
Consult with Engineer.
13.
Determine if more than stripping is required.
of general excavation if required.
14.
If wall drainage is required, provide either a drainage panel
(use Section 02711) or 1'-0" of 3/8" stone surrounded with
geotextile filter fabric (No. 4557 by Amoco Fabrics and
Fibers Company).
Add geotextile and stone to list of
product data and samples. The stone shall have the following
gradation, which may be altered if porous piping is not used,
and shall be listed under Article 2.01:
Sieve Size
1/2"
3/8"
No. 4
No. 8
No. 16
No. 35
Specify depth
Percent Passing by Weight
100
90-100
15-30
0-15
0-5
0
15.
If it is known that load bearing tests or additional borings
will be required, indicate in Article 3.09 that the
Contractor should allow for time to complete these items when
scheduling the project (so as not to claim a delay).
16.
Verify with geotechnical engineer that the 3’-0” fluctuation
in water level indicated in paragraph 3.02 C.3 is appropriate
for the specific project.
17.
Add references to soil remediation sections as required for
the project.
NYCSCA
EARTHWORK 02200 - 52
12/05/14
DESIGN No. _____
18.
If configuration of the site does not permit the stockpiling
or staging of soil at the site, insert site-specific options
for handling soil. Options may include, but are not limited
to, analytical results from the Phase II Environmental Site
Investigation, additional in-situ subsurface testing or
staging soil in roll-offs or other containers that may be
relocated from the work area to another on-site location.
19.
Modify the paragraph to reflect the presence of petroleumcontaminated material or hazardous waste present at the site,
if appropriate.
If petroleum-contaminated material or
hazardous waste is present at the site, add references to
soil remediation sections as required for the project
20.
The specified erosion control measures deal with Contractor’s
responsibility to provide basic erosion control for any
project,
which
shall
be
based
on
the
erosion
and
sedimentation control plan required to be provided in the
documents by the Designer of Record.
For projects over 1
acre requiring a full SWPP application, include specific
additional erosion and sediment control measures based on the
Contracts Documents that implement the approved full SWPP
plan filed with DEC.
21.
Omit for projects where compliance with NYC Green Schools
Rating System is not required (Typical of CIP projects).
Verify for referenced project.
22.
If a sub-slab depressurization system is not required, delete
gas permeable aggregate.
23.
Replace reference to Section 02081 with Scope Asbestos Survey
if the project is a Design/Build.
24.
Approval by the agencies indicated in the paragraphs is
required for work within the categories listed and must be
submitted to Building Department prior to plan approval.
Delete paragraphs that are not applicable to the work of the
project.
25.
If sub-slab depressurization system is required, coordinate
with design team to delete or modify references to interior
slab(s) since gas permeable aggregate will be installed.
26.
If existing soil on a site is known not to meet the
requirements for Unrestricted Use at 6 NYCRR 375-6, modify to
require import only of soil (no option for reuse) which meets
Unrestricted Use criteria.
27.
Coordinate with IEH Division on deletion or modification of
this section. Also coordinate with the use of 02091 and/or
02115 if a CAMP is specified in those sections.
Typical
language in 02091 and 02115 includes a reference to the CAMP
in 02200.
NYCSCA
EARTHWORK 02200 - 53
12/05/14
DESIGN No. _____
28.
Article 1.05 is referred throughout this document by number.
If article numbers and paragraphs within change for any
reason, ensure that the article and reference numbers change
accordingly throughout this specification.
29.
If during the design it is determined that a temporary
protection scheme that may involve tiebacks is required and
thus will require items to permanently remain on adjoining
property, discussions and agreements for such must be made
with the adjoining owners during design, which must be
arranged through the Construction Management division.
30.
Discuss
with
geotechnical
engineer
during
document
preparation and for historic structures or other structures
that may be in delicate condition indicate the appropriate
allowable acceleration.
31.
Monitoring plan is required if subsurface operations are
conducted that may impose loads or movement on adjoining
property or may be needed based on conditions or agreements
with adjacent owners or agencies (most new building work).
Refer to Sections BC 3309.6 and BC 3309.4.4.
Delete
requirement for monitoring plan if conditions that require
such plan are not required by Sections BC 3309.6 and
BC 3309.4.4 and project conditions.
GR:IEH:gr
NYCSCA
EARTHWORK 02200 - 54
12/05/14
DESIGN No. _____
LIST OF SUBMITTALS
SUBMITTAL
DATE SUBMITTED
DATE APPROVED
Product Data:
______________
_____________
______________
_____________
1.
2.
Compaction equipment
Filter fabric for silt fence
Shop Drawings:
1.
2.
3.
27
4.
5.
Underpinning/Shoring
Engineer's report on dewatering
Erosion and Sedimentation
Control Plan and narrative
Silt Fence
Community Air Monitoring Plan
Samples:
22
1.
2.
3.
4.
5.
22
22
7.
8.
9.
_____________
______________
_____________
______________
_____________
Project photographs
Survey logs and bench marks
Monitoring Plan
Certificates:
1.
2.
3.
4.
5.
6.
______________
Fill and backfill
Aggregate base
Crushed stone
Gas Permeable Aggregate
Broken stone ballast
Recycled concrete material
composition
Existing Conditions Survey:
1.
2.
3.
_____________
Fill and backfill
Aggregate base
Crushed stone
Gas Permeable Aggregate
Broken stone ballast
Design Data:
1.
2.
3.
4.
5.
6.
______________
Fill and backfill
Aggregate base
Crushed Stone
Broken stone ballast
Gas Permeable Aggregate
Recycled concrete material
Composition
Facility permits
Environmentally clean fill
Certificate for borrow site
Environmentally clean fill
Certificate for each load
NYCSCA
EARTHWORK 02200 - 55
12/05/14
DESIGN No. _____
Qualifications
1.
2.
_____________
Contractor
Professional Engineer
Testing:
1.
2.
3.
______________
_____________
Excavated material
classification for disposal
Existing material to remain
environmentally clean
Environmentally clean fill
and backfill
Documentation of Proper Disposal______________
_____________
Excavated Material Disposal
Plan
_____________
1.
2.
3.
______________
Non-Hazardous Excavated Material
Petroleum-contaminated
material (if required)
Hazardous waste (if required)
Sustainability:
1.
2.
3.
4.
______________
_____________
Sediment and erosion
control plan
Documentation of
Implementation of plan
Contractor’s Sustainable
Materials Form (see Section
S01352)
Mfr’s printed literature
or statement on recycled and
regional material content
* * *
NYCSCA
EARTHWORK 02200 - 56
12/05/14
DESIGN No. _____
Template 1A
Specification Section 02200
Environmentally Clean Fill/Backfill Criteria
Template for Summarizing Results of Analyses
Sites with No Ecological Resources
METALS
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
(mg/kg)
(mg/kg)
Arsenic
13
16
Barium
350
400
Beryllium
7.2
47
Cadm ium
2.5
4.3
Chrom ium , hexavalent
1
19
Chrom ium , trivalent
30
180
Cobalt
30
30
Copper
50
270
Cyanide (total)
Iron
Lead
27
27
2,000
2,000
63
400
Manganese
1,600
2,000
Mercury (total)
0.18
0.73
Nickel
30
130
Selenium
3.9
4
2
8.3
Silver
Vanadium
100
100
Zinc
109
2,480
NYCSCA
Insert Sam ple ID No.
Insert Date of Sam ple Collection
Insert Laboratory ID No.
Insert Laboratory Nam e and ELAP No.
EARTHWORK 02200 - 57
12/05/14
DESIGN No. _____
Insert Sam ple ID No.
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
Insert Date of Sam ple Collection
(mg/kg)
(mg/kg)
Insert Laboratory Nam e and ELAP No.
2,4,5-T
1.9
1.9
2,4,5-TP Acid (SILVEX)
3.8
3.8
2,4-D (2,4-Dichloro-phenoxyacetic acid)
0.5
0.5
PESTICIDES
4,4'-DDD
0.0033
13
4,4'-DDE
0.0033
4,4'-DDT
0.0033
8.9
7.9
Aldrin
0.005
alpha-BHC
0.02
alpha-Chlordane
0.094
beta-BHC
0.036
2.9
0.09
delta-BHC
0.04
0.25
Dibenzofuran
6.2
59
0.005
0.1
Endosulfan I 1
2.4
24
Endosulfan II 1
2.4
24
Dieldrin
Endosulfan sulfate
1
Endrin
Insert Laboratory ID No.
0.097
0.02
2.4
24
0.014
0.06
gam m a-BHC (Lindane)
0.1
0.1
gam m a-Chlordane
0.54
0.54
Heptachlor
0.042
0.38
Heptachlor epoxide
0.02
0.02
Methoxychlor
100
100
Parathion
1.2
1.2
0.1
1
POLYCHLORINATED BIPHENYLS (PCBS)
Aroclor-1016
Aroclor-1221
Aroclor-1232
Aroclor-1242
Aroclor-1248
Aroclor-1254
Aroclor-1260
Aroclor-1262
Aroclor-1268
1
The SCO is the sum of endosulfan I, endosulfan II and endosulfan sulfate.
NYCSCA
EARTHWORK 02200 - 58
12/05/14
SEMIVOLATILE ORGANIC COMPOUNDS
DESIGN No. _____
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
(mg/kg)
(mg/kg)
2,4,5-Trichlorophenol
0.1
0.1
2,4-Dichlorophenol
0.40
0.40
2,4-Dinitrophenol
0.2
0.2
2,6-Dinitrotoluene
1.0
1.0
2-Chlorophenol
100
100
2-Methylnaphthalene
0.41
0.41
2-Nitroaniline
0.4
0.4
2-Nitrophenol
0.3
0.3
3-Nitroaniline
0.5
0.5
4-Chloroaniline
0.22
0.22
4-Methyl-2-pentanone
1.0
1.0
4-Nitrophenol
0.1
0.1
Acenaphthene
20
98
Acenaphthylene
100
100
Aniline
0.33
0.33
Anthracene
100
100
Benzo(a)anthracene
1
1
Benzo(a)pyrene
1
1
Benzo(b)fluoranthene
1
1
Benzo(g,h,i)perylene
100
100
Benzo(k)fluoranthene
0.8
1.7
Benzoic Acid
2.7
2.7
Bis(2-ethylhexyl)phthalate
50
50
Butylbenzyl-phthalate
100
100
Chloroethane
1.9
1.9
Chrysene
1
1
Dibenz(a,h)anthracene
0.33
0.33
Diethylphthalate
7.1
7.1
Dim ethylphthalate
27
27
Di-n-butylphthalate
8.1
8.1
Di-n-octylphthalate
100
100
Fluoranthene
100
100
Fluorene
30
100
Hexachlorobenzene
0.41
0.41
Indeno(1,2,3-cd)pyrene
0.5
0.5
Isophorone
4.4
4.4
m -Cresol (3-Methylphenol)
0.33
0.33
Naphthalene
12
12
Nitrobenzene
0.17
0.17
o-Cresol (2-Methylphenol)
0.33
0.33
p-Cresol (4-Methylphenol)
0.33
0.33
Pentachlorophenol
0.8
0.8
Phenanthrene
100
100
Phenol
0.33
0.33
Pyrene
100
100
NYCSCA
Insert Sam ple ID No.
Insert Date of Sam ple Collection
Insert Laboratory ID No.
Insert Laboratory Nam e and ELAP No.
EARTHWORK 02200 - 59
12/05/14
VOLATILE ORGANIC COMPOUNDS
1,1,1-Trichloroethane
DESIGN No. _____
Specification Section
02200 Maxim um Reporting
Lim it
Insert Sam ple ID No.
Insert Date of Sam ple Collection
(mg/kg)
Insert Laboratory Nam e and ELAP No.
0.68
1,1,2,2-Tetrachloroethane
0.6
1,1-Dichloroethane
0.27
1,1-Dichloroethene
0.33
1,2,3-Trichloropropane
0.34
1,2,4-Trichlorobenzene
3.4
1,2,4-Trim ethylbenzene
3.6
1,2-Dichlorobenzene
1.1
1,2-Dichloroethane
0.02
1,3,5-Trim ethylbenzene
8.4
1,3-Dichlorobenzene
2.4
1,3-Dichloropropane
0.3
1,4-Dichlorobenzene
1.8
1,4-Dioxane
0.1
2,6-Dinitrotoluene
0.17
4-Methyl-2-Pentanone
1.0
Acetone
0.05
Benzene
0.06
Carbon Disulfide
2.7
Carbon Tetrachloride
0.76
Chlorobenzene
1.1
Chloroform
0.37
cis-1,2-Dichloroethene
0.25
Ethylbenzene
1
Freon 113 (1,1,2-TFE)
6
Hexachlorobenzene
0.33
Isopropylbenzene
2.3
Methyl ethyl ketone (2-Butanone)
0.12
Methyl tert-butyl ether (MTBE)
0.93
Methylene chloride
0.05
n-Butylbenzene
12
n-Propylbenzene
3.9
p-Isopropyltoluene
10
sec-Butylbenzene
11
tert-Butylbenzene
5.9
Tetrachloroethene
1.3
Toluene
0.7
trans-1,2-Dichloroethene
0.19
Trichloroethene
0.47
Vinyl Chloride
0.02
Xylene (m ixed)
0.26
NYCSCA
Insert Laboratory ID No.
EARTHWORK 02200 - 60
12/05/14
DESIGN No. _____
Template 1B
Specification Section 02200
Environmentally Clean Fill/Backfill Criteria
Template for Summarizing Results of Analyses
Sites with Ecological Resources
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
METALS
(mg/kg)
(mg/kg)
Alum inum
10,000
10,000
Antim ony
12
12
Arsenic
13
13
Barium
350
400
Beryllium
7.2
10
Boron
0.5
0.5
Cadm ium
Calcium
2.5
4
10,000
10,000
Chrom ium , hexavalent
1
1
Chrom ium , trivalent
30
41
Cobalt
20
20
Copper
50
50
Cyanide (total)
27
27
Iron
2,000
2,000
Lead
63
63
Lithium
2
2
Manganese
1,600
1,600
Mercury (total)
0.18
0.18
Molybdenum
2
2
Nickel
30
30
Selenium
3.9
3.9
Silver
Technetium
2
2
0.2
0.2
Thallium
5
5
Tin
50
50
Uranium
5
5
Vanadium
39
39
Zinc
109
109
NYCSCA
Insert Sam ple ID No.
Insert Date of Sam ple Collection
Insert Laboratory ID No.
Insert Laboratory Nam e and ELAP No.
EARTHWORK 02200 - 61
12/05/14
DESIGN No. _____
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
Insert Sam ple ID No.
Insert Date of Sam ple Collection
(mg/kg)
(mg/kg)
Insert Laboratory Nam e and ELAP No.
2,3,7,8-TCDD
0.000001
0.000001
2,3,7,8-TCDF
0.000001
0.000001
2,4,5-T
1.9
1.9
2,4,5-TP Acid (SILVEX)
3.8
3.8
2,4-D (2,4-Dichloro-phenoxyacetic acid)
0.5
0.5
4,4'-DDD
0.0033
0.0033
4,4'-DDE
0.0033
0.0033
4,4'-DDT
0.0033
0.0033
Aldrin
0.005
alpha-BHC
0.02
0.097
0.02
alpha-Chlordane
0.094
beta-BHC
0.036
PESTICIDES
Biphenyl
1.3
0.09
60
60
Chlordecone (Kepone)
0.06
0.06
delta-BHC
0.04
0.04
Dibenzofuran
6.2
59
0.005
0.006
Endosulfan I 1
2.4
24
Endosulfan II 1
2.4
24
Dieldrin
Endosulfan sulfate
1
Insert Laboratory ID No.
2.4
24
Endrin
0.014
0.014
Furan
600
600
gam m a-BHC (Lindane)
0.1
0.1
gam m a-Chlordane
0.54
0.54
Heptachlor
0.042
0.14
Heptachlor epoxide
0.02
0.02
Methoxychlor
1.2
1.2
Parathion
1.2
1.2
0.1
1
POLYCHLORINATED BIPHENYLS (PCBS)
Aroclor-1016
Aroclor-1221
Aroclor-1232
Aroclor-1242
Aroclor-1248
Aroclor-1254
Aroclor-1260
Aroclor-1262
Aroclor-1268
1
The SCO is the sum of endosulfan I, endosulfan II and endosulfan sulfate.
NYCSCA
EARTHWORK 02200 - 62
12/05/14
DESIGN No. _____
Specification Section
02200 Criteria for Cover
Material
Specification Section 02200
Criteria for Non-Contact
Material
SEMIVOLATILE ORGANIC COMPOUNDS
(mg/kg)
(mg/kg)
1,2,3,6,7,8-HCDF
0.00021
0.00021
2,3,4,5-Tetrachlorophenol
20
20
2,3,5,6-Tetrachloroaniline
20
20
2,4,5-Trichloroaniline
20
20
2,4,5-Trichlorophenol
0.1
0.1
10
10
2,4-Dichlorophenol
0.40
0.40
2,4-Dinitrophenol
0.2
0.2
2,6-Dinitrotoluene
1.0
1.0
2-Chlorophenol
0.8
0.8
2-Methylnaphthalene
0.41
0.41
2-Nitroaniline
0.4
0.4
2-Nitrophenol
0.3
0.3
3,4-Dichlorophenol
20
20
3-Chloroaniline
20
20
3-Chlorophenol
7
7
3-Nitroaniline
0.5
0.5
4-Chloroaniline
0.22
0.22
4-Methyl-2-pentanone
1.0
1.0
4-Nitrophenol
0.1
0.1
Acenaphthene
20
20
Acenaphthylene
100
100
Aniline
0.33
0.33
Anthracene
100
100
Benzo(a)anthracene
1
1
Benzo(a)pyrene
1
1
Benzo(b)fluoranthene
1
1
Benzo(g,h,i)perylene
100
100
Benzo(k)fluoranthene
0.8
1.7
Benzoic Acid
2.7
2.7
Bis(2-ethylhexyl)phthalate
50
50
Butylbenzyl-phthalate
100
100
Chloroethane
1.9
1.9
2,4,6-Trichlorophenol
Chrysene
1
1
Dibenz(a,h)anthracene
0.33
0.33
Diethylphthalate
7.1
7.1
Dim ethylphthalate
27
27
Di-n-butylphthalate
0.014
0.014
Di-n-hexyl-phthalate
0.91
0.91
Di-n-octylphthalate
100
100
Fluoranthene
100
100
Fluorene
30
100
Hexachlorobenzene
0.41
0.41
Indeno(1,2,3-cd)pyrene
0.5
0.5
Isophorone
4.4
4.4
m -Cresol (3-Methylphenol)
0.33
0.33
Naphthalene
12
12
Nitrobenzene
0.17
0.17
o-Cresol (2-Methylphenol)
0.33
0.33
p-Cresol (4-Methylphenol)
0.33
0.33
Pentachloroaniline
100
100
Pentachlorophenol
0.8
0.8
Phenanthrene
100
100
Phenol
0.33
0.33
Pyrene
100
100
NYCSCA
Insert Sam ple ID No.
Insert Date of Sam ple Collection
Insert Laboratory ID No.
Insert Laboratory Nam e and ELAP No.
EARTHWORK 02200 - 63
12/05/14
DESIGN No. _____
VOLATILE ORGANIC COMPOUNDS
1,1,1-Trichloroethane
Insert Sam ple ID No.
Insert Date of Sam ple Collection
(mg/kg)
Insert Laboratory Nam e and ELAP No.
0.6
1,1-Dichloroethane
0.27
1,1-Dichloroethene
0.33
10
1,2,3-Trichlorobenzene
20
1,2,3-Trichloropropane
0.34
1,2,4-Trichlorobenzene
3.4
1,2,4-Trim ethylbenzene
3.6
1,2-Dichlorobenzene
1.1
1,2-Dichloroethane
0.02
1,2-Dichloropropane
700
1,3,5-Trim ethylbenzene
8.4
1,3-Dichlorobenzene
2.4
1,3-Dichloropropane
0.3
1,4-Dichlorobenzene
1.8
1,4-Dioxane
0.1
2,4-Dichloroaniline
100
2,6-Dinitrotoluene
0.17
3,4-Dichloroaniline
20
4-Methyl-2-Pentanone
1.0
Acetone
0.05
Benzene
0.06
Carbon Disulfide
2.7
Carbon Tetrachloride
0.76
Chloroacetam ide
2
Chlorobenzene
1.1
Chloroform
0.37
cis-1,2-Dichloroethene
0.25
Dibrom ochlorom ethane
10
Ethylacetate
48
Ethylbenzene
1
Freon 113 (1,1,2-TFE)
6
Hexachlorobenzene
0.33
Hexachlorocyclopentadiene
10
Isopropylbenzene
2.3
Methanol
6.5
Methyl ethyl ketone (2-Butanone)
0.12
Methyl tert-butyl ether (MTBE)
0.93
Methylene chloride
0.05
n-Butylbenzene
Insert Laboratory ID No.
0.68
1,1,2,2-Tetrachloroethane
1,2,3,4-Tetrachlorobenzene
NYCSCA
Specification Section
02200 Maxim um Reporting
Lim it
12
n-Nitrosodiphenylam ine
20
n-Propylbenzene
3.9
Pentachlorobenzene
20
Pentachloronitrobenzene
10
p-Isopropyltoluene
10
sec-Butylbenzene
11
Styrene
300
tert-Butylbenzene
5.9
Tetrachloroethene
1.3
Toluene
0.7
trans-1,2-Dichloroethene
0.19
Trichloroethene
0.47
Vinyl Chloride
0.02
Xylene (m ixed)
0.26
EARTHWORK 02200 - 64
12/05/14
DESIGN No. _____
Template 2
Excavated Materials Disposal Plan (EMDP)
(Insert School/Site Name and Address)
(Date)
NYCSCA
EARTHWORK 02200 - 65
12/05/14
DESIGN No. _____
General notes regarding this template:
1. The EMDP must be signed by a Certified Hazardous Materials Manager approved by the
Institute of Hazardous Materials Management in Rockville, Maryland, or Qualified
Environmental Professional, approved by the Institute of Professional Environmental
Practice, Pittsburgh, Pennsylvania, or similar board-certified profession.
2. Directions to EMDP preparers are provided within this template as bold and italicized
text. In general, bold and italicized text indicates where information unique to the Site is
to be inserted by the writer.
NYCSCA
EARTHWORK 02200 - 66
12/05/14
DESIGN No. _____
Table of Contents
Title
Page
Introduction
A. Pre-Excavation Utility Surveys
B. Waste Characterization Sampling
C. Management of Excavated Soil
D. Disposal Facilities and Waste Transporters
E. Quality Assurance/Quality Control
F. Signature of Certified Preparer
List of Figures
Figure 1 – Site Plan
Figure 2 – Waste Characterization Sampling Plan
List of Appendices
Appendix A – Health and Safety Plan
Appendix B – Waste Transporter Permits
Appendix C – Disposal Facility Permits and Supporting Documentation (including a copy of the
NYSDEC Part 360 Permit or equivalent out of state regulatory agency permit)
NYCSCA
EARTHWORK 02200 - 67
12/05/14
DESIGN No. _____
Introduction
This Excavated Materials Disposal Plan (EMDP) describes the procedures to be followed for the
characterization, excavation, management, transportation and disposal of material excavated at
____________________ (insert Site name and location) in accordance with SCA Specification
Section 02200 (change to 02201, if applicable), (insert Design # and date). This work will be
performed by ___________________ (insert name of excavation contractor) under contract
with _________________________ (insert name of general contractor, if applicable).
Project activities associated with this EMDP include the characterization, excavation,
management, transportation, and disposal of approximately ______ (insert amount) cubic yards
of non-hazardous excavated material (change to appropriate category if the EMDP is being
prepared for non-hazardous industrial waste, petroleum contaminated material, and/or
hazardous waste) for the construction of the _________________ (insert project type – new
school, addition, flood elimination project, etc.).
All material excavated from the Site is assumed to meet the definition of non-hazardous
excavated material (change to appropriate category if the EMDP is being prepared for nonhazardous industrial waste, petroleum contaminated material and/or hazardous waste).
According to Specification Section 02200, Section 1.04, the following definitions apply to this
project: (conform below with the project specifications)
Non-Hazardous Excavated Material
Material that may include or contain mixtures of the following: soil (including, but not limited to,
natural undisturbed material), debris, concrete and concrete products (including steel or fiberglass
reinforcing rods that are embedded in the concrete), asphalt pavement, brick, glass, rock, municipal
solid waste, refuse, and incidental ash. This material includes material defined in Title 6 New York
Code of Rules and Regulations 360-7.1(b)(i) and will exceed 6 NYCRR 375-6 Unrestricted Use
and Restricted Use Soil Cleanup Objectives and NYSDEC CP-51: Soil Cleanup Guidance
Supplemental Soil Cleanup Objectives.
All material excavated from the site is assumed to meet the definition of non-hazardous excavated
material.
Petroleum-Contaminated Material
Material (soil, concrete, sediment, UST contents, fill, debris, etc.) that meets the NYSDEC STARS
Memo #1 definition of petroleum-contaminated material from known source areas. Petroleumcontaminated material shall be evidenced by the following observations and be from a known
source area: producing higher than background responses on a portable vapor meter such as a
photo ionization detector or flame ionization detector, petroleum-like odor, visual impacts (e.g.,
staining or discoloration), proximity to known releases from existing or historic petroleum storage
tanks or systems, and exceed the soil cleanup levels for gasoline and/or fuel oil contaminated soil
provided in the NYSDEC CP-51: Soil Cleanup Guidance. The determination as to whether the
excavated material is petroleum-contaminated or is non-petroleum contaminated material will be
made by analytical testing of representative material samples. All sampling shall be performed
under the supervision of the Authority’s IEH Division or its representative. The Contractor shall
provide the IEH Division with qualitative and quantitative information, and the IEH Division shall
make the final determination as to whether or not the material is petroleum-contaminated and the
appropriate disposal.
NYCSCA
EARTHWORK 02200 - 68
12/05/14
DESIGN No. _____
Hazardous Waste
Material meeting the definition of a Resource Conservation and Recovery Act hazardous waste as
defined in 40 CFR Part 261, New York State ECL Section 27-09 or 6 NYCRR Part 371.
Environmentally Clean Fill and Backfill
Refer to Section 02200 for definition and requirements associated with fill and backfill.
NYCSCA
EARTHWORK 02200 - 69
12/05/14
A.
DESIGN No. _____
PRE-EXCAVATION UTILITY SURVEYS
1. Describe how buried utilities (e.g. electric, gas, water, sewers, telephone, etc.) will be
located and marked out.
2. Describe how utility mark-out information will be provided to the Authority.
3. Confirm appropriate contact will be made with underground facilities protective
organizations in accordance with applicable laws and regulations.
NYCSCA
EARTHWORK 02200 - 70
12/05/14
B.
DESIGN No. _____
WASTE CHARACTERIZATION SAMPLING
Waste characterization samples will be collected and analyzed in accordance with the proposed
disposal facility(ies) requirements, outlined in Section D.
(Describe the type of soil sampling – i.e., will the sampling be performed in-situ [with a
Geoprobe] or will samples be collected from excavated stockpiles.)
Describe the soil sampling frequency and analyte list. For example, use text such as…
A total of ___(insert number) soil samples will be collected for analysis. This number of soil
samples equates to one sample for every 500 cubic yards (change as required based on disposal
facility requirements) of excavated material. Each sample will be analyzed for the following
parameters:







Volatile organic compounds (VOCs) by USEPA Method 8260
Semi-volatile organic compounds (SVOCs) by USEPA Method 8270
Polychlorinated biphenyls (PCBs) by USEPA Method 8082
Pesticides via USEPA Method 8081
Herbicides via USEPA Method 8151
RCRA Metals via USEPA Method 6010
Mercury via USEPA Method 7471
In addition, a total of ___(insert number) samples, one soil sample for every 5,000 cubic yards
(change as required based on disposal facility requirements), will be collected and analyzed for
the following parameters:


RCRA Characteristics
Full TCLP
Introduce and provide a to-scale site plan (Figure 1). Figure 1 shall show the site, an outline
of the proposed new construction, proposed excavation areas, and quantities of excavated
materials.
Introduce and provide a to-scale sampling plan (Figure 2). Figure 2 shall show the Site, the
locations on the Site where soil samples shall be collected, and which discrete soil samples shall
make up composite sample(s), as applicable. Note that the Figure should show sampling grids
with estimated average depths of excavation in each grid.
Discrete grab samples will be collected for VOCs. A five-point (change as required based on
disposal facility requirements) composite sample will be collected for all other analytes listed
above. Samples will be analyzed by _____________________________ (insert name and
address of laboratory), a New York State Department of Health Environmental Laboratory
Approval Program (ELAP) -certified laboratory.
After sample collection, the soil samples will be shipped to the NYSDOH ELAP certified
NYCSCA
EARTHWORK 02200 - 71
12/05/14
DESIGN No. _____
laboratory in chilled coolers, and accompanied by appropriate chain of custody records.
Analytical results will be provided to the proposed disposal facilities for their review and
approval. In addition, the results will be submitted to the NYCSCA’s IEH Division. A letter on
________(insert excavation contractor name) letterhead will be provided to the NYCSCA that
states that all available analytical data has been provided to the disposal facility. The disposal
facility(ies) will provide an original signed letter indicating that the soil meets the acceptance
criteria for their facility(ies) and the excavated material is accepted for disposal. This letter will
be forwarded to the NYCSCA upon receipt.
NYCSCA
EARTHWORK 02200 - 72
12/05/14
C.
DESIGN No. _____
MANAGEMENT OF EXCAVATED SOIL
(Describe the procedures for excavation work – for instance, number and types of excavators?
Is there any hand excavation work anticipated?)
On-site personnel involved in excavation activities shall comply with applicable Occupational
Safety and Health Administration (OSHA) rules and regulations, New York City Department of
Buildings (NYCDOB) requirements, and the Health and Safety Plan (HASP) presented as
Appendix A to this EMDP.
Excavated soil, if not directly loaded into trucks for transportation and disposal, will be
stockpiled on-site. Stockpiles will be placed on and covered with heavy duty tarps secured by
sand bags.
Dust suppression will be performed during work activities where the potential for elevated dust
conditions exists. Water will be used to spray/mist excavation areas in these instances. There
will be no visible dust emissions from the work areas. Other dust suppression techniques which
may be utilized include speed limits for trucks in unpaved areas, maintenance of Site paving as
long as practical, and minimization of excavation activities during periods of high winds. (Note
– if a community air monitoring program [CAMP] is required by the specifications, briefly
describe the CAMP requirements and implementation.)
NYCSCA
EARTHWORK 02200 - 73
12/05/14
D.
DESIGN No. _____
DISPOSAL FACILITIES AND WASTE HAULERS
Excavated material transportation will be performed by licensed transporters with valid
NYSDEC 6 NYCRR 364 Waste Transporter Permits. All proposed disposal facilities shall be
listed on the waste transporter permits.
Loaded vehicles leaving the Site will be appropriately
cleaned, lined, and covered in accordance with applicable laws and regulations. The proposed
licensed transporters with valid 6 NYCRR 364 Permits for this project are as follows:




Transporter 1 Name and Address
NYSDEC Part 364 Waste Transporter Permit # and Date of Expiration –
Disposal Facilities permitted for transport to Transporter 2 Name and Address
NYSDEC Part 364 Waste Transporter Permit # and Date of Expiration –
Disposal Facilities permitted for transport to Transporter 3 Name and Address
NYSDEC Part 364 Waste Transporter Permit # and Date of Expiration –
Disposal Facilities permitted for transport to Add additional haulers as necessary
Please refer to Appendix B for copies of the waste transporter permits.
Non-hazardous excavated material shall be transported to an off-site disposal facility meeting the
requirements of 6 NYCRR Part 360 or equivalent out-of-state facility approved by the appropriate
regulatory agency of that State with a permit to receive non-hazardous excavated material. (Note change to appropriate category if the EMDP is being prepared for non hazardous industrial
waste, hazardous waste and/or petroleum contaminated material).
The proposed disposal facilities meeting the criteria described above for this project are as
follows:




Disposal Facility 1 Name and Name of Owner
Address and Phone Number Type of Permit (i.e., Part 360?, NJDEP?, etc.)
Disposal Facility 2 Name and Name of Owner
Address and Phone Number Type of Permit (i.e., Part 360?, NJDEP?, etc.)
Disposal Facility 3 Name and Name of Owner
Address and Phone Number Type of Permit (i.e., Part 360?, NJDEP?, etc.)
Add additional disposal facilities as necessary
Please refer to Appendix C for copies of the disposal facility permits and soil testing
requirements, and acceptance criteria for each proposed disposal facility.
Waste characterization data will be provided to the proposed disposal facilities for their review
and approval. An original signed approval letter from each disposal facility will be submitted to
NYCSCA
EARTHWORK 02200 - 74
12/05/14
DESIGN No. _____
the NYCSCA IEH Division at least 48 hours prior to transportation and off-site disposal.
If the excavated material is rejected by the above proposed disposal facilities for any reason, an
alternate disposal facility (including required documentation) meeting the requirements of the
Specification Section 02200 (note – change to 02201, as applicable) will be proposed for
NYCSCA IEH Division’s consideration.
NYCSCA
EARTHWORK 02200 - 75
12/05/14
DESIGN No. _____
E.
QUALITY ASSURANCE/ QUALITY CONTROL
A qualified person will coordinate and manage the sampling and analysis program, management,
transportation, and disposal of excavated materials from the Site. _______________ (insert
name of the qualified person and the excavation firm responsible for these activities) will
direct these activities.
Laboratories used will be NYSDOH ELAP certified laboratories. The laboratories will
communicate directly with the samplers regarding the analytical results and reporting and will be
responsible for providing all labels, sample containers, trip blanks, shipping coolers, and
laboratory documentation.
Periodic quality assurance/quality control (QA/QC) audits of the EMDP will be performed by the
Contractor, and may also be performed by the NYCSCA, or the NYCSCA’s auditors. Any items
noted to be in non-compliance will be documented and audit findings will be presented to
____________________ (insert name of excavation firm) for resolution (with a copy to the
NYCSCA IEH Division). Verification of resolution(s) will be determined through re-inspecting
or re-auditing the non-compliant item.
All records regarding the removal and disposal of excavated materials shall be maintained by
____________________ (insert name of excavation firm) at the project site. These records will
be made available to the NYCSCA or their designated representatives at their request. Shipping
manifests and/or bills of ladings for excavated material will be provided to the NYCSCA on a
daily basis.
NYCSCA
EARTHWORK 02200 - 76
12/05/14
F.
DESIGN No. _____
SIGNATURE OF CERTIFIED PREPARER
_________________(insert name, certification) has prepared this EMDP for the
__________________________________ (insert site name, address, and type of work being
performed) in accordance with the requirements of Specification Section 02200 (change to
02201, if applicable). Additionally, _______________________ (insert name) hereby certifies
that (he/she) is a currently licensed/certified _______________________ (insert correct
certification - Certified Hazardous Materials Manager approved by the Institute of Hazardous
Materials Management in Rockville, Maryland, or Qualified Environmental Professional,
approved by the Institute of Professional Environmental Practice, Pittsburgh, Pennsylvania, or
similar board-certified profession).
PREPARED BY:
Name
Certification and Certification Number
NYCSCA
EARTHWORK 02200 - 77
12/05/14
DESIGN No. _____
FIGURES
NYCSCA
EARTHWORK 02200 - 78
12/05/14
DESIGN No. _____
APPENDIX A
HEALTH AND SAFETY PLAN
NYCSCA
EARTHWORK 02200 - 79
12/05/14
DESIGN No. _____
APPENDIX B
WASTE TRANSPORTER PERMITS
NYCSCA
EARTHWORK 02200 - 80
12/05/14
DESIGN No. _____
APPENDIX C
DISPOSAL FACILITY PERMITS AND SUPPORTING
DOCUMENTATION
(including a copy of the NYSDEC Part 360 Permit or equivalent out of state regulatory agency
permit)
NYCSCA
EARTHWORK 02200 - 81
Download