SECTION A – FALL 2026 MGMT 361
Name: _______________________________
Career Account: ____________________
Section:______________________________
Student code of conduct will be strictly enforced during this quiz. No talking during and after the quiz. No electronics
(except calculator) are allowed to be on or visible. No cheat sheet. When time is called, all writing utensil must be put
down immediately. This quiz contains 2 questions.
Question 1 (6 points total)
M1~M3 represent 3 workers at Chipotle. The hourly capacity for M3 is already calculated for you
in the right table.
Stage
M1 and M2
M3
M1
Capacity
?
18 [unit/min]
M3
M2
Stage 1
Stage 2
a) M1’s activity time is 4 second per unit. What is the capacity of M1 in [units/min]? (1 point)
[Formula: Resource capacity=1/Resource activity time]
b) M2’s activity time is 5 second per unit. What is the capacity of M2 in [units/min]? (1 point)
[Formula: Resource capacity=1/Resource activity time]
c) What is the cycle time of Stage 1 (M1 and M2) in [seconds/unit]? (Round the answer to 2
decimal places) (2 points) [Formula: Stage CT = 1/stage capacity]
d) What is the process capacity in [units/min]? (2 points) [Formula: Process capacity =
Bottleneck capacity]
SECTION A – FALL 2026 MGMT 361
Question 2 (4 points total)
An assembly-line process has five tasks as listed in the table below:
Task 1
Task 2
Task 3
Task 4
Task 5
Task time
25 sec
25 sec
30 sec
20 sec
20 sec
Three workers (S1, S2, S3) are staffed to this assembly line, and the assignment of tasks to each
workers is:
•
•
•
S1 does Task 1 and Task 2.
S2 does Task 3 and 4.
S3 does Task 5.
a) What is the capacity for each worker in [units/hour]? (2 points)
[Formula: Resource capacity=1/Resource activity time]
b) Assume a wage rate of $36 per hour. What is the direct labor cost in [$/unit]? (2 points)
[Formula: direct labor cost = Total wages/Process capacity.]