ASSIGNMENT #7
QUESTION 1
The following data have been collected for Sustainability Office UTM IT project for
two-week reporting periods 2 through 12.
a) Compute the SV, CV, SPI and CPI for each period.
b) What is your assessment of the project at the end of period 12?
QUESTION 2
The following labor hour’s data have been collected for a nanotechnology project
for periods 1 through 6. Compute the SV, CV, SPI, and CPI for each period. What is
your assessment of the project at the end of period 6?