Geo-Frontiers 2011 © ASCE 2011 56 Geotechnical Aspects for Design and Performance of Floating Foundations S. Mohsenian1, A. Eslami2 and A. Kasaee3 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. 1 Geotechnical Engineer, Department of Civil Engineering, Guilan University, IRAN; email: s_mha2004@yahoo.com 2 Associate professor, Department of civil Engineering, Amirkabir University of Technology, Aut, Tehran, IRAN; PH (98) 21-64543057; email: afeslami@aut.ac.ir 3 Structural Engineer, Department of Civil Engineering, Guilan University, IRAN; email: adelkasaee@yahoo.com ABSTRACT Floating foundations are often practical when foundations must be placed over deposits of compressible soil and when deep foundations are expensive. The aim of the present paper is to study parameters affecting the behavior of floating foundations, including the kind of floating foundations, depth of excavation, and imposed pressure by the superstructure. Herein, 3 buildings ranging from 15 to 25 stories with gross foundation pressures from 195Kpa to 342Kpa with similar area plan, 40m × 50m, are studied for 4 soil types ranging from very soft to strong type. Their foundations are studied by using numerical method of finite element. Moreover five case histories have been studied based on their records and analytical predictions. Results indicate that in case of low bearing capacity and high settlement, the floating foundations can be chosen as a reasonable alternative considering of technical and economical aspects. INTRODUCTION The building load can be carried on spread or strip footings, on a raft or mat foundations, or on piles. If the soil is weak and for the given load there is a risk of shear failure below the foundation, then the loads must be reduced, carried to a stronger underlining layer by piles. Alternatively, the applied load can be reduced utilizing a floating foundation, in which a total or partial superstructure load can be compensated by excavating the soil. The technique of reducing the total and differential settlement of a foundation by decreasing the net applied load by excavation is called floatation. When the weight of a structure is partly compensated by excavation, the building is said to be partially floating; when it is entirely compensated the building is fully floating. Floatation schemes are often practical when foundations must be placed over deep deposits of compressible soil and when deep foundations are expensive. If basement space is required, floatation is particularly attractive. Although the idea of floating foundations was known in the early nineteenth century, the principle was little used until the early twentieth century. The first reference to the concept of a floating foundation in the technical literature is Albion Mills built in 1783-86 in London. The building of Empress Hotel in Geo-Frontiers 2011 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. Geo-Frontiers 2011 © ASCE 2011 57 Victoria, British Colombia is the first case in which the principle was consciously used, although was not used in the original design (Crawford et al., 1971). The first built example of a floating foundation in the literature is the Ohio Bell Telephone Company Building constructed in 1925 in Cleveland. The Albany Telephone Building, which was built in 1929, is the first fully documented case of a foundation in which the principle of floatation was deliberately used in design (Glick, 1936). The most interesting cases come from Mexico city, where the problem is complicated by the general area settlement of the ground surface, such as Tower Latino Americana building (Zeevaert, 1957), where a group of 8 buildings between 18 to 22 m high including basement and an 86 m high tower were constructed over a 7 m deep partially floating box foundation (Rodriguezet et al., 2009). In this paper the parameters affecting the behavior of floating foundations are studied by a numerical method, including the kind of floating foundations, depth of excavation, and the pressure that is imposed by structures. Additionally, the records for five case histories will be reviewed. PERFORMANCE OF FLOATING FOUNDATION The principle of a floating foundation involves balance of weights only, and the foundation itself can consist of spread footings, a raft, a box, piles, or cylinders, or in some cases a combination of these. Problems of design and construction of floating foundation consist of excavation, water lowering, bottom heave, settlement, and structure problems. Excavation for a floating foundation involves the complete removal of the pressure originally against the soil at the base level of the foundation. As a consequence, the bottom of the excavation rises. During the subsequent period of construction, the weight of the building becomes equal to and on occasion exceeds the original overburden pressure; hence, the heave disappears, and the building settles. If the building has a greater weight than the excavated soil, the settlement passes through two stages. The first lasts until the load per unit of area at the base of foundation becomes equal to the original overburden pressure, and the second begins when this pressure is exceeded, i.e. recompression and virgin compression. The amount of heave and subsequent settlement depend upon the nature of the subsoil and the depth of excavation. The function of a raft foundation is to spread the load over as wide as possible, and to give a measure of rigidity to the sub-structure to enable it to bridge over local areas of weaker or more compressible soil. The degree of rigidity given to the raft also reduces differential settlement. Floating foundations are designed on the same principles, but they have additional and important function in that they utilize the principle of floating to reduce the net load on the soil. In this way the total settlement of the foundation is reduced and follows that, differential settlements will also be reduced. In view of spreading load of structure over the area, floating foundations include establishing raft foundations in depth which can be supported by retaining walls and also combination of raft and basement floor slab with walls (floating box foundation). In floating box foundation the vertical load is transferred from the upper structure to the basement through structural walls, and the maximum bending moment in the raft slab are used to define the reinforcement of this slab, due to the contact pressures, as the same as Geo-Frontiers 2011 Geo-Frontiers 2011 © ASCE 2011 58 design the slab of raft floating foundation. The upper slab is actually reinforced for loads due to car parking or warehouse storage. Floating foundations allow the substructure to be used for various purposes such as warehouse storage or underground car parks. This requires reasonably large floor areas without close-spaced walls or columns, and the floor generally consists of a slab or slab and beams of fairly heavy construction to give the required degree of rigidity. Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. MODELING APPROCH FOLLOWED For studying parameters affecting the behavior of floating foundations, 3 buildings ranging from 15 to 25 stories with 40 m × 50 m in plan with 10 m column spans are examined for 4 types of soil. The soil properties are shown in Table 1. The soil thickness beneath the foundations was 80 m, and the groundwater level was at the ground surface. The pressures at foundation level were 195, 264 and 342 Kpa for 3 buildings with 15, 20 and 25 stories respectively. The overall thickness of floating box foundations, were 3.6, 3.8 and 4 m with 0.4, 0.6 and 0.8 m thick raft slab and 0.3 m thick upper slab for them. The thicknesses of raft of floating raft foundations for buildings with 15, 20 and 25 stories were 1.8, 2.1 and 2.3 m respectively. Table 1. Soil properties used in numerical analysis Soil type 1 2 3 4 Saturated density, KN/m3 20 20 18 18 19.5 19.5 17 17 Friction, degree 35 30 25 18 Drained shear strength, Kpa 50 30 15 15 Poison ratio 0.3 0.3 0.3 0.3 Elasticity index, Mpa 50 35 20 5 Unsaturated density, KN/m3 The foundations are studied by using numerical method of finite element. The calculation stages of numerical method consist of initial conditions, excavation stage, construction of the basement, and activation of loads. EXCAVATION DEPTH AND KINDS OF FLOATING FOUNDATION To assess the effect of excavation depth and the type of floating foundation on the amount of settlement, the raft and box foundations were floated to various depths from the surface of the ground, in 4 types of soil. Each case was analyzed for the maximum settlement. The vertical displacements were used directly; with a downward vertical displacement considered as positive. The retaining wall depth was 2 m greater than excavation depth and the thickness of it was 1m. The diagrams of maximum settlements of foundations with the retaining walls for 3 groups of construction with 15, 20 and 25 stories floated in 4 types of soil are shown in Figures 1-a to 1-c. At a superficial depth of Geo-Frontiers 2011 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. Geo-Frontiers 2011 © ASCE 2011 59 ground, the amount of maximum settlement would be high, and by increasing the excavation depth the settlement could be reduced to allowable limits. The reasons for this case can be mentioned in this manner that after removal the overburden pressure in the result of excavating and replacing with the imposed pressure from the structure, the amount of remaining net pressure at the base of foundation will be reduced. By decreasing is the weight (the reason for the settlement), the amount of maximum settlement can be reduced. After all, by increasing the excavation depth, the amount of settlement will reach to zero. This depth is equal to the full floating depth (i.e. the imposed pressured from the structure has been equivalent with the equal pressure of excavated overburden pressure and the amount of the remaining net pressure will be negligible at the base of foundation and the amount of the settlement). Also, as shown in Figure 1, after achieving the full floating depth in the case of foundation installing at the lower depth, the bottom of the excavation rises, because of the reduced pressure imposed from the structure with the pressure of excavated overburden pressure. This depth is not suitable for foundation establishment. Moreover, it is notable that for each group of the constructions floated in each type of soil, types 1 to 4, the type of raft and box foundations was not very influential on the amount of total settlement and also in depth of full floatation. Really, in the similar conditions in the manner of excavation depth, the imposed pressure from the structure and conditions of subsoil, the amount of maximum settlements are almost similar in two types of foundation. 1-a 1-b Geo-Frontiers 2011 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. Geo-Frontiers 2011 © ASCE 2011 60 1-c Figure 1. Effect of excavation depth and kind of floating foundation with retaining wall a) 15 storey building b) 20 storey building c) 25 storey building. The information related to the depth of fully floating and allowable settlement has been shown in Table 2. Table 2. Depth of fully floating and depth to reach to allowable settlement Depth for, m 15 story 20 story 25 story fully floating, m Satisfy settlement, m fully floating, m Satisfy settlement, m fully floating, m Satisfy settlement, m soil 1 plain box 11 11 6 5 14.5 15 8.5 7.5 18.5 19 12 11.5 soil 2 soil 3 soil 4 plain box plain box plain box 11 11 11.5 12 12.5 12 6.5 5.5 8.5 7 10.5 9.5 14.5 15 15.5 15.5 15.5 15.5 10 8.5 11.5 10.5 13.5 12.5 18.5 19 20 20 20 20.5 13 12 14.5 14 16.5 16 PRESSURE IMPOSED BY STRUCTURES The diagrams of maximum settlements of the floating foundations with retaining walls under the impression of pressure of construction with 15, 20 and 25 stories in four types of soil have been shown in Figures 2-a to 2-d. As illustrated in Figures 2-a to 2-d, considering that the excavation depth is fixed, by increasing the number of storey, the amount of maximum settlement will be increased, and the foundation will get to full floating in more depth. This is because of this case that by increasing the storey of the building, the imposed pressure from them will be increased. Considering that the excavation depth is fixed, by increasing the amount of imposed pressure from the structure, the amount of the remaining of the net pressure on subsoil will be increased. Geo-Frontiers 2011 Geo-Frontiers 2011 © ASCE 2011 61 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. 7-a 7-b 2-a 2-b 2-c 2-d Figure 2. Effect of pressure imposed by 15 to 25 storey buildings on different soils a) Type 1 b) Type 2 c) Type 3 d) Type 4. CASE STUDIES Followings are the brief history of some typical cases of floating foundations to confirm the results of finite element analysis to measured values. The predicted settlement of the cases with finite element analysis, are shown in Table 4. Case No. 1 [Somerville et al., 1972] The sites proposed for six blocks of 15 storey flats in the Parkhead and Bridgeton districts of Glasgow are underlain by deep alluvial deposits consisting of firm laminated clays and silts, with deeper deposits of sands, gravels and glacial drift followed by the productive coal measures. Accordingly, partially floating box foundations were adopted to reduce the bearing pressure on the clays and silts. In this paper we studied one block of Geo-Frontiers 2011 Geo-Frontiers 2011 © ASCE 2011 62 Bridgeton (BBS) of this Complex. The building, 27 m × 16 m in plan, is located 4.3 m below the ground surface. The average gross unit load transmitted to the foundation is 135 KPa. The average net unit load transmitted to the foundation is 50 KPa. The observed maximum settlement for the block at the Brigeton is 6 cm. Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. Case No. 2 [Brown, 1972] The Life Science building (LSA) is a reinforced concrete frame with curtain-wall construction consisting of two basements, eight floors. The building is located on the east end of the MIT campus. The structure measures 66.5 m × 18 m in plan, with gross weight of the structure amounts to intensity of area load of 213 KPa. The subsoil consists of fill, silt, sand, gravel, Boston blue clay and till. The foundation was designed as a fully floating foundation, located in 10 m below ground surface. The observed maximum settlement for the building is about 0.3 cm. Case No. 3 [Brown, 1972] The site of the Student center is located on the MIT campus (SCA). The center is a 5-story reinforced concrete frame structure, with one basement, measuring about 43 m × 71 m in plan. The gross unit weight of the structure distributed uniformly over the foundation is about 107.5 KPa. The subsoil consists of fill, silt, sand, gravel, Boston blue clay and till. The foundation was designed as a fully floating foundation, located in 5 m below ground surface. The observed maximum settlement for the building is 0. Case No. 4 [Lopes et al., 1994] A reinforced concrete structure was built to house two large emergency dieselpower generators at the Angra dos Reis nuclear power plant in the state of Rio de Janeiro, Brazil (PGB). The structure is rectangular in plan (16.6m × 27m) and is 9 m high with three 0.5 m thick external walls. The total structural loading, including the power generators and other installations, is 55 MN, Which corresponds to an average vertical contact pressure of 123 KPa. The foundation was designed as a box foundation of overall thickness 4.5 m, with a 1.3 m thick ground slab and a 0.4 m thick upper slab. The subsoil, include medium-dense sand, was investigated by dynamic standard penetration tests, cross-hole and laboratory tests. The subsoil profile is shown in Figure 3. The observed settlement for the building after 3 years of construction was 2 cm. Case No. 5 [Wong et al., 1995] The Raffles City Complex, constructed in Singapore, is a comprehensive property development comprising four high-rise structures and a 7-storey podium. There is a three storey basement beneath the whole complex. The four towers are framed reinforced concrete structures with internal concrete shear walls. The four towers in Raffles City Complex are supported on individual floating raft foundations. In this paper we studied Tower C (TCS) of this Complex. The subsoil consists of fine to coarse sand fill from the ground surface down to depth 4 m depth and of the Boulder Clay down to a depth of Geo-Frontiers 2011 Geo-Frontiers 2011 © ASCE 2011 63 more than 70 m. the engineering properties of the clay is given in Table 3. The water table is located about 2 m below the ground surface. The 2.8 m thick raft for the tower which is 57.7 m × 60.8 m, is located 17.5 m below the ground surface. The average gross unite load transmitted to the foundation is 439 KPa. The average net unit load transmitted to the foundation is 201 KPa. The settlement of the tower was monitored at regular intervals during the construction. The maximum settlement of the tower is 4.8 cm. Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. Table 3. Soil parameters for the Bouldery Clay (Wong et al., 1995) project Raffles City complex Water content (percent) 10-20 Bulk density (KN/m3) 20-23 Young’s modulus (MPa) Undrained shear strength (KPa) 40-150 (95) 70-1150 (195) Figure 3. Subsoil profile of reinforced concrete structure, case No. 4 (Lopes et al., 1994) Table 4. Cases built on floating foundation foundation NO. Case Location type depth (m) Area (m2) pressure (Kpa) number of stories Soil profile Silt & clay Boston blue clay Boston blue clay observed settlement (mm) Predicted settlement (mm) 60 67 3 7 0 7 1 BBS Scotland Box 4.3 27*16 135 15 2 LSA America Raft 10 66.5*18 213 10 3 SCA America Raft 5 43*71 107.5 6 4 PGB Brazil Box 4.5 16.6*27 123 - Sand 20 26 76 Bouldery clay 48 57 5 TCS Singapore Raft 17.5 57.7*60.8 Geo-Frontiers 2011 439 Geo-Frontiers 2011 © ASCE 2011 64 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. CONCLUSION In this paper the parameters affecting the behavior of floating foundations have been studied by numerical method. Also five case histories were compiled and the measured settlement compared with predicted values. The following results have been achieved: (1) Increasing the excavation depth will be reduced the amount of maximum settlement foundations, because of reducing the net pressure on the subsoil. (2) Amount of maximum settlements will be high at the depth of ground surface and the settlement will be reduced to allowable limits by increasing the excavation depth. After all, by increasing more excavation depth, the fully floating depth is reached. (3) Increasing the number of storey, considering that the excavation depth is fixed, amount of maximum settlement will be increased and the foundation will reach to fully floating in more depth, because of increasing the net pressure on subsoil. (4) The predicted settlements of some typical case histories of floating foundation with finite element method are compared with the observed settlements of the cases and are within the observed settlement. REFFERENCE Brown, T.L. (1972). Comparison of calculated versus measured pereformance of floating foundations at MIT. ScD Thesis, Dept. of Civil Engineering, MIT, Cambridge, Mass,179p. CFEM. (1992). Canadian geotechnical society, 3th ed., Bitech. Publishers, Vancouver, 512p. Chung, S.G., Kwag, J.M., Beak, S.H. and Lee, N.K. (2005). "Performance of a medium tall building supported by a floating foundation on the Nakdong river deltaic deposit." J. KSCE journal of civil engineering, Geotechnical Engineering, No. 3, Vol. 9: 187-195. Crawford, C.B. and Sutherland, J.G. (1971). "The Empress hotel sixty-five years of foundation settlements." Can. Geotech. Jour: 78-93. Fang, H.G. (2001). Foundation engineering handbook. 3th ed., CBS :537-555. Glick, G.W. (1936). "Foundations of the new telephone building." Proc. 1st Int. Conf. S.M.F.E., Cambridge, Mass :287. Hemsley, J.K. (2000). Design applications of raft foundation. Tomas Telford, 626p. Lopes, F.R., Souza. S.N., and Soares. E.S. (1994). "Long-term settlement of a raft foundation on sand." Proc. Instn. Civ. Engng: 11-16. Rodrigues, N.P., Lopes, A., and Auvient, G. (2009). "3D numerical modeling of the behavior of large buildings founded on Mexico city soft clay." Geotechnics of soft soils, Taylor and Francis group, London :87-94. Somerville, S.H., and Shelton, J.C. (1972). "Observed settlement of multi-storey buildings on laminated clays and silts in Glasgow." Geotechnique, Vol. 22 :513520. Tomlinson, M.J. (2001). Foundation design and construction. 7th ed., CEng FICE, Geo-Frontiers 2011 Geo-Frontiers 2011 © ASCE 2011 65 Downloaded from ascelibrary.org by Arizona State Univ on 05/24/14. Copyright ASCE. For personal use only; all rights reserved. FIStructE, 569p. Wong, I.H., Ooi, I.K., and Broms, B.B. (1996). "Performance of raft foundations for high-rise buildings on the Bouldery clay in Singapore." Can. Geotech, Vol. 33 : 219-236. Zeevaert, L. (1957a). "Foundation design and behavior of Tower Latino Americana in Mexico city." Geotechnique, Vol. 2 : 115-133. Geo-Frontiers 2011